Pay attention to us now! Recently, some netizens consulted about the transformation of the community through the “Baihu folk voice” Daqing network political platform      1.

When will the community environment be restored? On October 14, the reply of the municipal thermal power company is as follows: 1.

3.

Fabricated Frame Scaffold

The designed buried depth of heating pipeline is 1.2m.

Pay attention to the latest hot spots in Daqing every day, including cars, real estate, education, medical treatment…

After the completion of the project, the ground greening and ground of the community shall be restored by the construction unit according to the original state.

Construction machinery vehicles are driven freely on the road, and the greening and roads of the community are damaged.

Can the heat fee be reduced or exempted if the heat supply in green community is not provided on time due to construction? 2.

Due to the actual situation of the reconstruction project site, some sections can not meet the buried line requirements.

The content of the “public opinion” is from the original source, and the copyright is owned by the original source..

For the reconstruction of the old pipe network in green phase II, the bidding for construction materials will be carried out in the winter of 2020, and the heating period will end in 2021.

4.

The community is full of ditches without protection and warning signs.

Who is responsible for accidents? 3.

In case of accidents caused by this, our company and the construction unit are responsible.

In July this year, our company re invited bids for materials, determined the material supplier, gradually transported the pipes to the construction site in early September, and the construction bid winner started the project in September.

2.

Daqing hot spot information release media.

Source: “Daqing Lake Folk voice”, the official account of the network platform of Daqing.

Due to the rise in the price of bulk steel commodities, the bid winner of all materials abandoned the bid.

Does the outdoor buried depth of heating pipeline less than half a meter meet the specification requirements? 4.

For the problem that there are ditches and no protection and warning signs in the community, the construction unit is required to protect the ditches and unprotected places and set up warning signs.

If the heating is not provided on time due to construction, it can be reduced on a daily basis.