Construction daily report of section tjsg23 of phase II project of Xi’an Metro Line 6, Sunday, October 31, 2021, weather: overcast, 10 ~ 18 ℃.
The construction of shield section guide platform from Wanshou South Road station to satellite measurement and control center station is 3830383 meters.
The air push station meter of the shield section from the satellite measurement and control center station to tianjiawan station is 206.225 / / / / 206.225 hand hole caulking ring 988 / / / / / 974 left line excavation ring 425 / / 77100% 425 right line excavation ring 563007_ two 29%558 other matters 1.
Routine inspection of shield machine in Wei Tian section.
remarks on equipment input of construction personnel and management personnel of the project 10000 ~ Weitian shield interval___ Day shift of 1 tunneling team: 15 persons night shift: 15 persons day shift: 17 persons night shift: 15 persons (1) Herrick 1105# shield machine (2) Herrick 1106# shield machine_ Meet construction needs_ Day shift of 2 caulking team: 2 people (3) mg45 / 16t gantry crane (4) mg16t gantry crane to meet construction requirements; day shift of 3 plugging team: 0 people (5) super capacitor locomotive No leakage 4 civilized construction team day shift: 2 people (6) mortar mixing plant to meet construction needs 5 maintenance team Day shift: 0 (7) axial flow fans have not entered the site yet.
6、 Cause analysis and measures taken for failure of today’s plan None; 7、 Mobilization of equipment and materials today (1) material mobilization: no new mobilization materials; (2) Equipment mobilization: no new mobilization equipment; 8、 No memorabilia…
Chiseling of portal on the right line of Wei Tian section.
Shield machine removal on the left line of Wei Tian section; 4.
IV.
Other matters: the removal of guide platform formwork of the right line of concealed tunnel in Wanshou satellite measurement and control center station is completed_ 3、 Construction operation management personnel and equipment input No.
1、 Completion of output value (10000 yuan) 1 planned day completion date per capita output value weekly planned week completion Complete week Proportion / / 301033% planned to be completed in February Proportional year The cumulative annual completion rate of the planned year is 200105% 11440441238%.
Shield machine removal on the left line of Wei Tian section; 3.
II.
Welding of the receiving bracket of the right line in the satellite measurement and control center station to tianjiawan station; 2.
Other matters 1.
The completion of the construction progress.
Welding of receiving bracket on the right line of Wei Tian section.
safety production conditions of working faces at various work points of the project.
The portal of the right line of Wei Tian section is chiseled and the receiving bracket is welded.
The construction of guide platform in shield section from Wanshou South Road station to satellite measurement and control center station is 383 / / / / / 383 meters.
The design quantity of the project unit is completed on the planned day.
The planned monthly completion rate is completed on the planned month.
Erection of welding lug platform on the left line of Wei Tian section v Tomorrow’s construction plan the project unit plans to complete the inspection of the left line tunnel in the shield section from satellite measurement and control center station to tianjiawan station / / / inspection of the left line tunnel / / / left line tunnel / / / left line tunneling ring 4250425 and right line tunneling ring 5630558.
Erection of shield machine welding lug platform on the left line of Wei Tian section; 2.
Other matters: civilized construction at the receiving end of tianjiawan station.
The right line portal of Wei Tian section shall be chiseled out; 3.