Construction technology | from now on, the project manager, director and all key personnel shall not be changed or evacuated after winning

The supervision unit may appoint professional supervision engineers or supervisors to take charge of safety supervision, survey review and witness sampling.

Those who change or evacuate without authorization shall be dealt with in accordance with relevant regulations.

Key posts on the construction site include: Project Manager, technical director, constructor, quality officer Full time safety production management personnel (Safety Officer), documenter and labor management personnel; chief supervision engineer, chief supervision engineer representative, professional supervision engineer and supervisor dispatched by the supervision unit; also including construction project leader and design site leader (i.e.

This standard is the minimum staffing standard for key posts.

design site representative).

If the personnel are allocated by stages, the service stage of the personnel shall also be indicated.

If the project manager, the construction project leader of EPC project, the design site leader and the chief supervision engineer have one of the following circumstances, they will be recognized as failing to perform management Obligations: (I) the project manager, the person in charge of the construction project of the EPC project and the person in charge of the design site shall be on duty for less than 80% of the time that should be on duty, and the chief supervision engineer shall be on duty for less than 40% of the time that should be on duty; (II) he is absent from one quarter of the regular site meetings and more than half a year; (3) Failing to sign or affix the practicing seal on the documents related to project construction management in accordance with the requirements of laws, regulations or specifications, or being signed by others; (IV) failing to participate in the construction or acceptance of key nodes of divisional and subdivisional works in accordance with the requirements of laws, regulations or specifications; (5) Other circumstances stipulated by laws and regulations.

For complex sports venues, comprehensive projects and projects with tight construction period and multi shift construction operation, the number of constructors, quality personnel and full-time safety production management personnel shall be appropriately increased on the basis of the above allocation standards.

Star setting: enter the official account homepage and click on the top right corner.

For those who serve as chief supervision engineers of multiple construction projects at the same time, the supervision unit shall provide chief supervision engineer representatives in the on-site supervision department of each construction project they supervise..

3.

If you do not want to miss the highlight of this official account, please set the public address of the construction technology as the star sign and click “collect”, “look at” and “Zan” at the end of the text, so that each new article will appear in the subscription list at the first time.

2.

3.

4.

The key post personnel who have won the bid shall not participate in the bidding of other projects again.

Note: it is also proposed in the supervision and management measures for real name system of construction site personnel in the field of engineering construction in Hainan province that the personnel on the construction site must use attendance equipment for labor attendance every time they enter and leave the construction site.

Click Set as star, The yellow star can be seen around the official account of the yellow star (Android and iOS user operation).

On duty performance 1.

Personnel in key positions shall be implemented by face and other biometric technologies Name system information attendance, and the on-the-job time is calculated according to the attendance time recorded in the service platform.

When there are 2 or more full-time safety production managers, one of them shall participate in the safety management of mechanical lifting equipment; When there is one full-time safety production management personnel, full-time or part-time machinery management personnel shall be equipped.

In December 14th, the Hainan provincial housing and construction department issued the “Hainan province construction site key position personnel and the management of on-the-job duty”.

Scaffolding Walk Boards

In case of any of the following circumstances, it is determined that the performance of the project does not meet the requirements or fails to fulfill the management obligations after winning the bid: (1) the comprehensive average attendance time of personnel at key positions of the project is less than 50% of the time they should be on duty; (2) If the arrival time of personnel at key posts is lower than the requirements of the bidding documents or the contract.

2.

Explore the link between on-the-job performance and performance recognition.

4.

Annex 2: staffing standards for key posts on site of Hainan construction engineering supervision unit note: 1.

Except for 9 cases such as force majeure, Enterprise self winning From the date of signing the contract to the date of completing the quantities agreed in the contract, the project manager, chief supervision engineer of the contractor and all personnel in key positions of the project subject to bidding according to law shall not apply for change.

2.

Face and other biometric technologies are used for electronic punch in.

Performance time requirements: Project Manager of the contractor, construction project leader of EPC project and design site leader, The on-the-job performance time of the chief supervision engineer shall not be less than 80% of the on-the-job time (deducting the legal holidays); the on-the-job performance time of the chief supervision engineer for each project shall not be less than 40% of the on-the-job time (deducting the legal holidays); except for the above personnel, the personnel at other key positions of the project shall be on duty within the management responsibilities (22 days in principle).

2.

, effective as of the date of printing and distributing.

The tenderee shall, in the bid notice, indicate the name, position, qualification or relevant certificate number and ID number of the key post according to the tender document of the winning bidder.

Attendance method.

5.

Annex 1: staffing standards for key posts on site of construction engineering contractors in Hainan Province note: 1.

In the process of bid evaluation, the bid evaluation committee shall The staffing of key posts on the construction site shall be included in the review.

/ / official account official of WeChat / NOCITCE / WeChat changed the push rule because of the official account of WeChat.

If an enterprise participates in the bidding of a project, the key post personnel promised in the bidding document shall not be reused in the bidding of other projects from the date of submission of the bidding document to the end of bid evaluation.

3.

EPC project If the manager meets the requirements, he can also serve as the person in charge of the construction project.

This standard is the minimum staffing standard for key posts.

If the comprehensive average attendance time of personnel in key positions is less than 50% of the time they should be on duty, they will not be recognized as the performance of the enterprise.

If the project is under general contracting, the construction project leader, design site leader and other management personnel shall be allocated on this basis, and the EPC project department shall be established.