[daily learning] construction site safety checklist before Spring Festival shutdown. Attachment: safety management during the Spring

The production sewage and rainwater drainage systems are intact, and the sewer pipes are not blocked   Mechanical equipment 1.

2) Semi finished products: concrete (precast slab beam, main bridge 0# block, etc.), reinforcement cage, reinforcement framework, etc..

VII.

4.

The fire extinguisher shall be placed in the set position, placed stably, and the pressure or weight shall be normal; On site inspection 2.

3.

Eliminate all kinds of unsafe hidden dangers.

8.

The on-site finished product protection personnel must cooperate with each other during work, shall not act alone, remind each other and pay attention to safety.

Strengthen the entrance management of the project site, ensure that someone is on duty 24 hours, prevent and persuade outsiders to enter the construction site, and avoid unnecessary safety accidents.

7.

During the Spring Festival, we must pay attention to safety when setting off fireworks and firecrackers; Pay attention to food safety and prevent overeating; Pay attention to the snowy weather and pay attention to traffic safety when going out.

The problems found shall be handled in time and rectified seriously.

Time arrangement: the Spring Festival holiday is         year        month       Day (lunar calendar)      month      ﹚—-         year        month       Day (lunar calendar)      month      ) at      Oh, my God.

Arrange maintenance personnel, equipment and facilities, and strictly implement various maintenance measures.

The left behind personnel must be familiar with the project site, the emergency rescue plan of the project, the reserve of rescue materials, and ensure that they are on duty 24 hours in turn.

There is no potential safety hazard in water and gas; 3.

The appearance and door lock of switch box and distribution box are intact and locked; 4.

Before shutdown, all power cables on the project site must be cut off, and a comprehensive inspection must be conducted on the lighting, drainage and power supply lines to eliminate the explosion loss of electromechanical equipment.

   VIII.

The line is free of buried pressure and immersion phenomenon; 3.

11.

Relevant spare parts shall be prepared for equipment maintenance; 4.

Before shutdown, comprehensive self inspection and self correction must be carried out for all systems and links on the project site.

The monitoring room shall have a specially assigned person on duty for 24 hours, and timely report the situation to the management personnel on duty.

Before the Spring Festival holiday, do a good job in the safety and health work of the project department.

Strengthen the storage of inflammables and explosives, especially the safe use of fire and electricity in the canteen, and arrange special personnel to be responsible for the management of the canteen.

Fire safety 1.

Ensure that the telephone is unblocked and answered within 24 hours; 3.

Scientifically arrange duty and patrol during holidays.

During the Spring Festival shutdown, all projects are shut down.

Colleagues from other places who take a bus home take good care of their belongings and valuables.

2.

Work arrangement during the Spring Festival holiday 1.

The personnel on duty shall not connect wires without permission or use electric furnaces and other heating equipment to prevent fire caused by power consumption.

6、 Protection and safety measures for semi-finished products during the Spring Festival 1.

Strengthen the security work to prevent damage by a few people, actively do their own safety work, especially strengthen the management of power consumption.

4.

Don’t buy the tickets of ticket dealers to avoid being cheated.

The duty place is the duty room of the project department and the site duty room.

The protection work and safety conditions shall be recorded in detail.

6.

Office and living quarters 1.

It’s time to go home for the Chinese New Year.

inspection items       Inspection standards and contents inspection methods inspection results meet or   Preventive measures for non conformities I.

Our project department establishes a safety leading group during the Spring Festival holiday to actively carry out self inspection and self correction of the project’s own safety before the holiday, and timely and comprehensively investigate all kinds of potential accidents.

4、 Safety measures on the construction site during the holidays 1.

Protection scope maintenance and protection measures for all finished products and semi-finished products of the project during the Spring Festival.

3.

The personnel of each dormitory and each department shall tidy up their personal and office articles and place them in order.

The storage of oxygen and acetylene shall meet the specified requirements.

Safety equipment and facilities are complete and effective; 4.

Electricity safety   1.

Cut off the power, close the window and lock the door.

Vi.

Formulate and distribute the list of personnel on duty at all levels; Check records   Check plan   2.

3、 On duty list during holidays: see the attached table.

The personnel on duty have understood the relevant contents of the emergency plan and disposal plan.

Turn off the computer and power switch.

Production equipment and facilities are in normal operation; 3.

When climbing, work according to the specification requirements.

There are no sundries in the distribution room and no blockage at the inlet and outlet.

7.

Spherical Head Anchor

It is required to check carefully according to the requirements of safety production and find out the nonconformities.

Construction site safety checklist before Spring Festival shutdown project item: inspection date: Inspector   (signature) objective to find out the nonconformities through the inspection before holidays, so as to formulate management measures, eliminate violations and ensure production safety during holidays.

In addition to paying attention to the site safety, the personnel on duty should also pay attention to self-protection, and timely report any problems to the superior management personnel on duty.

5.

Those that cannot be rectified shall be reported in time and corresponding preventive measures shall be taken.

The person in charge of each department and office shall sort out the office items, place them in order, carefully check and clean them.

10.

Doors and windows are normal, undamaged and sealed; On site inspection 2.

I   Establish a safety production leading organization and a safety leading group during the Spring Festival holiday   Leader: Deputy Leader: Cheng   Clerk: II.

13.

Arrange 4 personnel to be responsible for the safety inspection and protection of the project department and the site, and 10 personnel to be responsible for the protection of on-site finished products and semi-finished products and on-site drainage.

emergency safety 1.

II.

The emergency rescue system can operate normally and respond immediately in case of accidents; On site inspection 2.

The workers’ dormitory shall not be occupied, all power switches shall be cut off, valuables shall not be placed, and doors and windows shall be locked to prevent theft.

  No.

Reasonably arrange the work and rest time during the holiday.

The fire passage is unblocked without sundries;    4.

Don’t deposit cash and valuables in the dormitory.

Work arrangement: during the holidays, all the projects will be shut down, and only the protection of finished and semi-finished products, on-site safety inspection and protection will be carried out.

If there is no power in both circuits, the generator must be started immediately to ensure the normal operation of the project department and the site land.

Power off and lock the equipment for shutdown; On site inspection 2.

   3.

Iron fence shall be placed at the entrance of the access road on the construction site, and the warning sign of “no entry” shall be hung.

12.

Strengthen the on-site monitoring work.

Fire fighting facilities are in good condition; Sufficient quantity for easy access; 3.

When buying tickets, please buy them at the regular window.

V.

It is strictly prohibited to leave their posts and go out during the shift.

Fireworks and firecrackers are prohibited on the construction site, and foreign personnel or vehicles are not allowed to enter the site.

6.

Prepare raw materials and auxiliary materials during holidays to ensure production and use; On site inspection 2.

2.

During the Spring Festival holiday, the management personnel of the left behind construction site shall implement the 24-hour shift system.

  5、 Other precautions during the holiday 1.

Formulate safety protection measures.

The standby equipment and equipment are in good condition and can be put into use at any time.

The line is standard and well fixed; On site inspection 2.

Security 1.

5.

Ensure the normal use of public living, production facilities and equipment during holidays; 3.

spare parts 1.

1) Raw materials: cement, sand, gravel, admixture, reinforcement, steel strand, anchorage, bellows, steel plate, sleeve, welding rod, geotextile, geogrid, support, steel pipe, section steel, etc.

The person in charge of the dormitory and each department shall do a good job in cleaning, cut off all power switches and close the doors and windows.

Pay attention to self-protection during holidays and improve safety awareness.

Once the external power supply is cut off, the standby power supply circuit must be started immediately.

2.

Grounding, neutral and leakage protection measures are in place; 5.

9.

3.

When leaving the construction site, carefully check and clean the dormitory, close the doors and windows, and check whether the air conditioner and power plug are turned off; Don’t put money and other valuables in the dormitory during holidays.

The configuration of emergency rescue device is complete and complete; 3.

8.

Other inspections safety management during the Spring Festival holiday in order to ensure safety during the Spring Festival holiday and effectively control the occurrence of various accidents.