Verification records of gas fire extinguishing system engineering quality control data.
5.
Data verification records and project quality acceptance records shall be filled in according to the requirements of Appendix D of this specification.
The project quality acceptance results shall be all qualified.
Inspection records of gas fire extinguishing system engineering construction process.
All data verification results shall be qualified.
4.
If the project of reworking or replacing system components and complete sets of devices still fails to meet the requirements, acceptance is strictly prohibited.
6.
The system engineering acceptance shall be carried out jointly by the construction, design, supervision and other personnel organized by the construction unit on the basis of the self inspection and evaluation of the construction unit.
2.
If the shape of the component is changed after repair, but it can meet the provisions of relevant standards and use requirements, it can be accepted according to the approved treatment technical scheme and agreement documents.
4.
5.
3.
2.
Relevant documents, records, data lists, etc.
(this article specifies the documents and data to be provided after the system project passes the acceptance, which is necessary to ensure the project quality and establish the project archives.
These two aspects can solve the problem and pass the acceptance; otherwise, it will not be accepted to ensure the project quality.) 3.0.9 The gas fire extinguishing system works that have not been accepted or fail to pass the acceptance shall not be put into use, and the gas fire extinguishing system put into use shall be maintained and managed.
3.
All inspection results during construction shall be qualified.
6.
Quality management inspection records on the construction site.
The acceptance results of concealed works shall be qualified.
The measuring instruments used for acceptance inspection shall have appropriate accuracy, pass the measurement verification and calibration by legal institutions and be within the validity period.
(this article specifies the treatment methods when the construction quality of the gas fire extinguishing system project does not meet the requirements, which is a problem that will be encountered in the construction process.
The inspection results of quality management on the construction site shall be all qualified.
3.0.5 The gas fire extinguishing system engineering acceptance shall comply with the following provisions: 1.
Before concealment, the construction unit shall notify relevant units for acceptance, and make acceptance records according to Appendix C of this specification.
2.
Gas fire extinguishing system engineering quality acceptance record.
It provides convenience for future verification.) 3.0.8 If the construction quality of gas fire extinguishing system engineering does not meet the requirements, it shall be handled according to the following provisions: 1.
2.
(the content of Chapter 3 is not much involved in the examination, but as the basic requirements of project construction, we can briefly understand it.) you’d better look at it..
3.
3.
4.
Acceptance records of concealed works.
3.0.7 After the system engineering is accepted, the following documents and data shall be provided: 1.
The rework is aimed at the process, the system components are replaced, and the complete set of devices are aimed at the hardware of the system.
3.0.6 The inspection and acceptance shall comply with the following provisions: 1.
The appearance quality of the project shall be inspected on site by the acceptance personnel and jointly confirmed.
5.
After the system engineering passes the acceptance, the construction unit shall submit the system engineering acceptance report and relevant documents to the relevant administrative departments for the record within the specified time.
Rework or replace the equipment, and re accept it.