General contracting project of medical complex building project of Longgang District Hospital of traditional Chinese medicine (Lot 2)

There are 231 boreholes in block F, including 0 boreholes today and 21 boreholes in total; 2 grouting: F202 and F201, 4 grouting completed in total, 210 remaining boreholes and 227 remaining grouting.

5、 No matters requiring the owner’s coordination..

6.

There are 296 boreholes in Block D, including 7 boreholes today: D72, d30, D71, D29, D66, D28 and d107, with a total of 55 boreholes; 0 grouting, 28 grouting completed in total, 241 remaining boreholes and 268 remaining grouting.

There are 332 boreholes in Block C, including 6 boreholes today: C47, C46, C45, C57, C58 and C59, with a total of 71 boreholes; 0 grouting, 39 grouting completed in total, 261 remaining boreholes and 293 remaining grouting.

Epidemic prevention material reserve.

3、 Site construction and inspection 1.

Anchor bolt construction within the scope of foundation pit complex building.

        There are 82 managers and workers in the project department.

Daily pre shift education.

4.

4.

Drilling and grouting construction in the west of foundation pit on October 31: there are 260 boreholes in area a, 0 boreholes today, and a total of 178 boreholes; There are 3 grouting: a91, a130 and A97, 169 grouting have been completed in total, 82 remaining boreholes and 91 remaining grouting.

A total of 502 boreholes and 380 grouting have been completed, 979 remaining boreholes and 1101 remaining grouting.

3.

Daily killing in office and living areas.

There are 231 boreholes in Block B, including 0 boreholes today and 177 boreholes in total; There are 5 grouting: B205, b194, B125, b178 and B204.

Closed management of the project, entry registration information of all personnel, temperature measurement, verification of health code and travel code.

2.

Excavation, demolition and outward transportation of the third layer of earthwork.

A total of 81 people were vaccinated, including 40 management personnel, 39 completed vaccination, and the remaining one was not vaccinated due to physical reasons; There are 34 on-site construction personnel, and 34 have been inoculated; There are 8 logistics personnel in total, and 8 have been vaccinated.

On site epidemic prevention 1.

3.

Vaccination and nucleic acid testing.

There are 131 in zone E.

There are 1481 boreholes in ABCDEF area, including 13 boreholes and 10 grouting today.

The earth and stone excavation between the second and third support of the third layer shall be broken and transported out.

2.

2.

On October 31, 18 carts of stonework were unearthed, with a total of 15716 carts, a total of 196450 cubic meters.

1、 Weather conditions II.

A total of 140 grouting have been completed, 54 remaining boreholes and 91 remaining grouting.

5.

Grouting construction and karst cave treatment in ABCDEF area within the scope of foundation pit complex building.

4、 Subsequent construction plan 1.

3.

Water level monitoring.

Lifting Pin Anchor

Four 42.5 bulk cement trucks arrived today, totaling 131210kg.