General contracting project of medical complex building project of Longgang District Hospital of traditional Chinese medicine (Lot 2)

Today, 4 trucks of 42.5 bulk cement were mobilized, totaling 124060kg.

3.

Excavation, demolition and outward transportation of the third layer of earthwork.

There are 231 boreholes in Block B, including 2 boreholes today: b137 and B138, with a total of 163 boreholes; 0 grouting, 134 grouting completed in total.

Anchor bolt construction within the scope of foundation pit complex building.

Epidemic prevention material reserve.

There are 322 boreholes in Block C, including 0 boreholes today and 58 boreholes in total; 0 grouting, and 36 grouting have been completed in total.

The third cement tank shall be hoisted on site.

There are 131 in zone E.

2.

A total of 81 people were vaccinated, including 40 management personnel, 39 completed vaccination, and the remaining one was not vaccinated due to physical reasons; There are 34 on-site construction personnel, and 34 have been inoculated; There are 8 logistics personnel in total, and 8 have been vaccinated.

5、 No matters requiring the owner’s coordination..

8.

Vaccination and nucleic acid testing.

Closed management of the project, entry registration information of all personnel, temperature measurement, verification of health code and travel code.

On site epidemic prevention 1.

There are 296 boreholes in Block D, including 4 boreholes today: d163, d162, d161 and D160, with a total of 40 boreholes; 6 grouting: D67, D69, d279, D160, d162 and d163, and 19 grouting have been completed in total.

On October 28, 11 carts of stonework were unearthed, with a total of 15644 carts of stonework unearthed, a total of 195550 cubic meters.

3.

4.

7.

3.

The third party inspection team of quality safety station of Longgang District came to inspect the project.

5.

3、 Site construction and inspection 1.

Grouting construction and karst cave treatment in ABCDEF area within the scope of foundation pit complex building.

2.

Daily killing in office and living areas.

Water level monitoring.

The earth and stone excavation between the second and third support of the third layer shall be broken and transported out.

There are 231 boreholes in block F, including 10 boreholes today: f208, f207, f199, F200, F206, F205, F201, F202, f204 and F203, with a total of 10 boreholes; 0 grouting, 0 grouting completed in total.

Magnet Recess Former

4、 Subsequent construction plan 1.

Daily pre shift education.

Today, there are 16 boreholes and 9 grouting.

        There are 82 managers and workers in the project department.

There are 1471 boreholes in ABCDEF area.

A total of 449 boreholes and 352 grouting have been completed.

4.

Drilling and grouting construction in the west of foundation pit on October 28: there are 260 boreholes in area a, 0 boreholes today, and a total of 178 boreholes; There are 3 grouting: a226, A196 and a44, and 163 grouting have been completed in total.

1、 Weather conditions II.

2.

6.