General contracting project of medical complex building project of Longgang District Hospital of traditional Chinese medicine (Lot 2)

Water level monitoring.

3.

A total of 81 people were vaccinated, including 40 management personnel, 39 completed vaccination, and the remaining one was not vaccinated due to physical reasons; There are 34 on-site construction personnel, and 34 have been inoculated; There are 8 logistics personnel in total, and 8 have been vaccinated.

        There are 82 managers and workers in the project department.

5、 No matters requiring the owner’s coordination..

There are 296 boreholes in area D, including 8 boreholes today: D15, D8, D16, D7, d17, D32, d73 and d31, with a total of 48 boreholes; There are 3 grouting: d260, d262 and d264.

There are 131 in zone E.

The earth and stone excavation between the second and third support of the third layer shall be broken and transported out.

Today, there are 24 boreholes and 12 grouting.

Commissioning and drilling of test roof bolter.

On site epidemic prevention 1.

Daily killing in office and living areas.

Epidemic prevention material reserve.

2.

Vaccination and nucleic acid testing.

There are 332 boreholes in Block C, including 7 boreholes today: c320, c324, c319, C313, c331, c312 and C332, with a total of 65 boreholes; There are 3 grouting: C150, C100 and c109, with 39 grouting completed in total, 267 remaining boreholes and 293 remaining grouting.

Fixing Socket Cross Hole Nail Plate

2.

Four 42.5 bulk cement trucks arrived today, totaling 128710kg.

Excavation, demolition and outward transportation of the third layer of earthwork.

Daily pre shift education.

6.

There are 231 boreholes in block F, including 4 boreholes today: F170, f169, F168 and f167, with a total of 21 boreholes; 2 grouting: f204 and F203, 2 grouting completed in total, 210 remaining boreholes and 229 remaining grouting.

Drilling and grouting construction on October 30 in the west of the foundation pit: there are 260 boreholes in area a, 0 boreholes today, and a total of 178 boreholes; 3 grouting: a125, A127, a89, 166 grouting completed in total, 82 remaining boreholes and 94 remaining grouting.

7.

Anchor bolt construction within the scope of foundation pit complex building.

4.

Grouting construction and karst cave treatment in ABCDEF area within the scope of foundation pit complex building.

There are 231 boreholes in Block B, including 5 boreholes today: b121, b124, B125, B104 and B103, with a total of 177 boreholes; One grouting: B205, 135 grouting completed in total, 54 remaining boreholes and 96 remaining grouting.

1、 Weather conditions II.

Closed management of the project, entry registration information of all personnel, temperature measurement, verification of health code and travel code.

3.

There are 1481 boreholes in ABCDEF area.

28 grouting have been completed in total, 248 boreholes and 268 grouting.

On October 30, 29 carts of stonework were unearthed, with a total of 15698 carts of stonework unearthed, a total of 196225 cubic meters.

4.

3、 Site construction and inspection 1.

2.

A total of 489 boreholes have been completed, 370 grouting, 992 remaining boreholes and 1111 remaining grouting.

3.

4、 Subsequent construction plan 1.

5.