General contracting project of medical complex building project of Longgang District Hospital of traditional Chinese medicine (Lot 2)

2.

4、 Subsequent construction plan 1.

There are 231 boreholes in block F, including 7 boreholes today: f213, f174, f175, f176, f177, f178 and f171, with a total of 17 boreholes; 0 grouting, 0 grouting completed in total, 214 remaining boreholes and 231 remaining grouting.

3、 Site construction and inspection 1.

A total of 465 boreholes, 358 grouting, 1006 remaining boreholes and 1113 remaining grouting have been completed.

There are 322 boreholes in Block C, including 0 boreholes today and 58 boreholes in total; 0 grouting, 36 grouting completed in total, 264 remaining boreholes and 286 remaining grouting.

In the basic test, three anchor bolts have been positioned (m43m55m84), and the anchor bolt machine and personnel have entered the site for construction.

1、 Weather conditions II.

A total of 25 grouting have been completed, 256 remaining boreholes and 271 remaining grouting.

7.

There are 296 boreholes in Zone D, including 0 boreholes today and 40 boreholes in total; There are 6 grouting: d278, d259, D261, D263, d161 and d169.

There are 231 boreholes in Block B, including 9 boreholes today: B139, b134, B133, b129, B130, B132, b131, B123 and b122, with a total of 172 boreholes; 0 grouting, 134 grouting completed in total, 59 remaining boreholes and 97 remaining grouting.

4 trucks of 42.5 bulk cement mobilized today, with a total of 130500kg.

A total of 81 people were vaccinated, including 40 management personnel, 39 completed vaccination, and the remaining one was not vaccinated due to physical reasons; There are 34 on-site construction personnel, and 34 have been inoculated; There are 8 logistics personnel in total, and 8 have been vaccinated.

Excavation, demolition and outward transportation of the third layer of earthwork.

On site epidemic prevention 1.

5.

The earth and stone excavation between the second and third support of the third layer shall be broken and transported out.

4.

There are 1471 boreholes in ABCDEF area, including 16 boreholes and 6 grouting today.

Closed management of the project, entry registration information of all personnel, temperature measurement, verification of health code and travel code.

Vaccination and nucleic acid testing.

Daily pre shift education.

3.

2.

2.

Grouting construction and karst cave treatment in ABCDEF area within the scope of foundation pit complex building.

5、 No matters requiring the owner’s coordination..

Thread Swivel Eye

There are 131 in zone E.

4.

        There are 82 managers and workers in the project department.

3.

Drilling and grouting construction in the west of foundation pit on October 29: there are 260 boreholes in area a, 0 boreholes today, and a total of 178 boreholes; 0 grouting, 163 grouting completed in total, 84 remaining boreholes and 97 remaining grouting.

On October 29, 25 carts of stonework were unearthed, with a total of 15669 carts of stonework unearthed, a total of 195862.5 cubic meters.

3.

Anchor bolt construction within the scope of foundation pit complex building.

Epidemic prevention material reserve.

6.

Water level monitoring.

Daily killing in office and living areas.