General contracting project of medical complex building project of Longgang District Hospital of traditional Chinese medicine (Lot 2)

2.

Leaders of the technical section of the works Department came to inspect the project.

A total of 81 people were vaccinated, including 40 management personnel, 39 completed vaccination, and the remaining one was not vaccinated due to physical reasons; There are 34 on-site construction personnel, and 34 have been inoculated; There are 8 logistics personnel in total, and 8 have been vaccinated.

Daily pre shift education.

The earth and stone excavation between the second and third support of the third layer shall be broken and transported out.

4.

Anchor bolt construction within the scope of foundation pit complex building.

Vaccination and nucleic acid testing.

There are 0 boreholes in Zone C, with a total of 58 boreholes; 5 grouting: C56, C148, c162, C55 and C101, and 36 grouting have been completed in total.

3.

Closed management of the project, entry registration information of all personnel, temperature measurement, verification of health code and travel code.

2.

2.

6.

Excavation, demolition and outward transportation of the third layer of earthwork.

        There are 82 managers and workers in the project department.

Epidemic prevention material reserve.

Today, 4 trucks of 42.5 bulk cement were mobilized, totaling 124060kg.

3.

Grouting construction and karst cave treatment in ABCDEF area within the scope of foundation pit complex building.

Drilling and grouting construction in the west of foundation pit on October 27: 0 boreholes in area a, with a total of 178 boreholes; 2 grouting: A100 and a90, and 160 grouting have been completed in total.

1、 Weather conditions II.

7.

3.

On October 27, 20 carts of stonework were unearthed, with a total of 15633 carts of stonework unearthed, a total of 195412.5 cubic meters.

15 boreholes in the South 1#~ 15# emergency grouting plugging of the first and second support room have been completed.

5、 No matters requiring the owner’s coordination..

On site epidemic prevention 1.

Daily killing in office and living areas.

5.

4.

4、 Subsequent construction plan 1.

There are 9 boreholes in area B: b168, B167, b148, B147, B146, B145, b141, B140 and B139, with a total of 161 boreholes; There are 2 grouting: B32 and B35, and 134 grouting have been completed in total.

Plate Anchor

3、 Site construction and inspection 1.

There are 0 boreholes in Zone D, with a total of 36 boreholes; 2 grouting: D256 and d265, and 13 grouting have been completed in total.

Water level monitoring.