How to divide the general subcontract construction interface? Vanke project example reference!

II.

Municipal works; 3.

Intelligent project.

the general contractor of the entrance door installation project shall be responsible for Reserve the entrance door according to the architectural and structural construction drawings, and be responsible for the painting and repair around the entrance.

12.

Swimming pool water treatment system engineering.

Telecommunication engineering; 9.

The general contractor is responsible for connecting the rainwater pipe, sewage pipe and waste water pipe to the first inspection well outside the monomer or the first inspection well outside the outer wall of the basement (excluding inspection well construction) X.

The general contractor shall be responsible for the construction of threading sleeve and wall repair of cable TV project; 2.

The door frame, door leaf and door leaf external decoration shall be implemented by the professional contractor, and the painting end of the fire door in the staircase shall be implemented by the general contractor.

13.

Fire protection works.

2、 Curtain wall, steel structure canopy, car ramp, bicycle ramp canopy project, unit door 1.

The general contractor shall be responsible for the unified procurement and installation of fire doors and fire hydrant doors of staircases and pipe shafts in the entrance hall and standard floor elevator hall according to the requirements of the professional contractor.

the general contractor of the wear-resistant floor project is responsible for the construction of the painted base to the wear-resistant floor, and deliver it to the professional contractor for construction after meeting the quality requirements of the wear-resistant floor.

Sign works; 4.

Cable TV project; 10.

The general contractor is responsible for the embedded construction of the installation hook of the civil air defense door; 2.

4、 Fine decoration works of public parts such as entrance hall and standard floor elevator hall 1.

Landscape engineering 1.

wall repair and other works; 2.

After the design scheme and construction drawings of the pipeline gas engineering are determined, the general contractor shall be responsible for embedding the casing according to the pipeline gas construction drawings in the main structure construction stage; 2.

The general contractor shall be responsible for embedding the embedded iron parts of balcony, balcony railing, air conditioning board railing or aluminum alloy louver according to the construction drawings of railing and louver, and hand them over to the professional contractor for construction after completing the preliminary painting.

The installation works of public parts such as entrance hall and standard floor elevator hall shall only be embedded and threaded by the general contractor in the concrete wall and concrete ceiling according to the construction drawings of strong and weak current, and others shall be implemented by the professional contractor; (this installation can also be implemented by the general contractor) 3.

Landscape works; 2.

V.

I.

The general contractor shall be responsible for the construction of the structural part and the installation reservation and embedding part of the landscape swimming pool.

Division of cross construction interface between the general contracting scope and the professional contracting project.

Civil air defense door and civil air defense equipment installation works.

Fire fighting works; 14.

Curtain wall, steel structure canopy, car ramp, bicycle ramp canopy project, unit door; 3.

Water works; 6.

After the connection construction between the professional contracting project and the embedded parts is completed, the general contractor shall complete the painting and repair.

After the bottom glass curtain wall is installed and fixed on the ground, the general contractor shall be responsible for closing; 5.

VI.

The general contractor shall be responsible for the threading casing of the telecommunication engineering .

The general contractor shall be responsible for the construction of fire prevention and blocking of bridges and weak current wells.

Night scene lighting works; 5.

contents of professional contracting works outside the scope of general contracting I.

Stereo garage; 12.

Xi.

The fire blocking of bridge and weak current well shall be constructed by the general contractor.

The general contractor shall also be responsible for the masonry of brick masonry in public parts (if the wall is painted with paint or real stone paint, the general contractor shall complete the painting of the wall base, and others shall not be painted); 2.

Telecommunication Engineering 1.

Intelligent engineering; 15.

1.

The construction unit of intelligent project has not been confirmed before the construction of main structure In the main structure construction stage, the general contractor shall be responsible for embedding electrical casing and casing through external wall, embedding and plugging, secondary piping and slotting repair according to the construction drawings of intelligent building engineering; (Note: before the construction of the main structure, the intelligent engineering construction unit has been determined.

3、 The general contractor of exterior wall coating and real stone paint works is responsible for the construction of anti crack mortar surface course to external insulation works.

VII.

1.

Pipeline gas engineering; 8.

aluminum alloy doors and windows Balcony and air conditioning aluminum alloy railing and aluminum alloy shutter works 1.

pipeline gas engineering 1.

Traffic sign works; 9.

Bend Loop

For the division of construction interface between the cross construction parts with the professional contracting, see the following text description: I.

The intelligent construction unit is responsible for embedding electrical casing and casing through external wall, embedding and plugging, secondary piping and slotting repair according to the construction drawings of intelligent building engineering in the construction stage of the main structure.) 2.

Door installation works; 7.

1.

The general contractor shall be responsible for the reservation of air duct interfaces and fire hydrant box holes in concrete and masonry structures; 2.

The general contractor is also responsible for embedding the lightning protection embedded parts of curtain wall lightning protection design in place; 2.

Exterior wall coating 4.

Solar energy equipment and installation works; 11.

Aluminum alloy doors and windows, balcony and air conditioning aluminum alloy railings (non aluminum alloy railings shall be implemented by the general contractor) and aluminum alloy louver works; 2.

The opening of the pipeline gas pipe through the floor or wall shall be constructed by the general contractor according to the requirements of the gas construction drawings.

VIII.

The general contractor is responsible for the construction of corresponding contents in the construction drawings of buildings and structures above the main outdoor floor and within the unit entrance door, as well as the rigid waterproof layer of the roof of the outdoor basement; 2 The professional contractor shall be responsible for the entrance steps of the external unit, ramps and railings for the disabled, the ground of the overhead floor and the decoration of the wall ceiling; 3.

The municipal unit shall be responsible for the filling above the rigid waterproof layer of the roof plate of the outdoor basement to the top elevation of the municipal rainwater and sewage pipe 2.

The general contractor is responsible for reserving the unit door opening according to the architectural and structural construction drawings, and painting and repairing the periphery of the opening.

The general contractor of power supply works shall be responsible for The whole system construction of strong current distribution equipment and pipelines from the back of the primary meter to each end and the casing embedding of high-voltage incoming line.

2、 Works directly contracted outside the scope of general contracting construction drawings 1.

Steel structure works.

The general contractor is responsible for the construction of embedded iron parts according to the construction drawings of car ramp and bicycle ramp canopy; 4.

Civil air defense door and civil air defense equipment installation works; 10.

The ground and ceiling of public parts such as entrance hall and standard floor elevator hall shall be constructed to the structural floor by the general contractor according to the architectural and structural construction drawings, and delivered to the professional contractor after ensuring the flatness of the ground and ceiling surface.

IX.

XIV.

The fire blocking of bridge and weak current well shall be constructed by the general contractor.

Cable TV project.

contents of professional contracting works within the scope of general contracting construction drawings 1.

Residential central air conditioning project; 11.

Power supply works; 7.

Municipal Engineering 1.

The general contractor is responsible for cooperating with the professional contractor in the installation of civil air defense equipment such as civil air defense doors and wartime plugging, as well as the embedding of civil air defense sleeves and the reservation of openings.

The general contractor is responsible for embedding iron parts in the main structure according to the construction drawing of steel structure canopy, and completing thermal insulation and painting repair after the construction of professional contracting project is completed; 3.

If there are steel frames, the professional contractor shall construct them, and the general contractor shall paint the walls around the openings and decorate the internal and external walls; The general contractor shall also be responsible for embedding the lightning protection embedded parts of the lightning protection design of doors and windows in place; 2.

The general contracting construction unit shall complete all work contents in the construction drawings of buildings, structures, water supply and drainage, electrical, HVAC and foundation pit enclosure except the above professional contracting scope.

The general contractor is responsible for embedding the embedded iron parts of curtain wall structure in the main structure according to the curtain wall construction drawing, and painting the outside of the embedded parts with antirust paint for treatment.

1.

Elevator equipment and installation works; 13.

Real stone paint project; 5.

Wear resistant floor works; 8.

The reserved hole and outgoing line connection of the primary meter box shall be the responsibility of the general contractor..

Fine decoration works of public parts such as entrance hall and standard floor elevator hall; 6.

The general contractor is responsible for reserving aluminum alloy door and window openings on the building facade above the outdoor floor according to the architectural and structural construction drawings, and the professional contractor completes the installation of aluminum alloy doors and windows.

Source: in case of infringement by Luban alliance of construction engineering, please contact to delete the example and share the detailed rules for the division of general subcontracting construction interface of Vanke project, which can be used for reference.

Stainless steel water tank and installation works; 12.

XV.

The general contractor shall be responsible for the construction of water pump foundation and waterproof blocking of reserved holes in roof air duct and shaft; the general contractor shall be responsible for the construction of fire emergency lighting system.