If the drainage facilities are damaged during construction, 300000 yuan will be fined for sewage discharge!

Guide [if you have a boss around you who wants to recruit technicians from the project department, please forward our applet to him! Every small move will change a life] the recruitment applet of the project department will review every recruitment information.

After investigation, the sewage in this area flowed into the second work area of lot 01 of Changchun urban rail transit line 6 project of China Railway 16th Bureau Group Co., Ltd., and the general contractor of the project was China Railway 16th Bureau Group Co., Ltd.

On October 18, law enforcement officers came to the site of the project and ordered the general contractor of the project, China Railway 16th Bureau Group Co., Ltd., to contact the person in charge of Changchun Juyi Construction Engineering Co., Ltd.

The person in charge of the general contractor of the project, China Railway 16th Bureau Group Co., Ltd.

During the inspection, the staff of the Drainage Department found that a large amount of mud water flowed into Leijia ditch through the drainage pipe at the intersection of Jingbei Road, Lvyuan District, Changchun and the West Fourth Ring Road, which had an impact on the downstream water environment of Changchun West Lake.

On October 20, the law enforcement personnel came to the second work area of lot 01 of the project again, and the project leader and the work area leader were not on the site of the work area.

If you are fooled, our legal team will escort you for free, please rest assured to apply for a job! On August 21, the municipal construction market law enforcement and Supervision Detachment received the relocation of the Drainage Department of the municipal construction commission.

the person in charge of the work area of the project said that he would report to the person in charge of the project, and did not give a clear reply on when to go to the detachment for the next law enforcement procedure, The person in charge of the project and the relevant person in charge of Changchun Juyi Construction Engineering Co., Ltd.

did not appear.

The law enforcement personnel started the law enforcement procedures against Changchun Juyi Construction Engineering Co., Ltd.

If the relevant units of the project continue to prevaricate, they will be submitted to the people’s court according to law…

The problems and prevarication attitude in the second work area of lot 01 of the project have attracted great attention of the municipal construction market law enforcement and Supervision Detachment.

The person in charge of the subcontractor lost contact, failed to make a statement and plead within the time limit, and did not apply for a hearing.

The detachment will cooperate with relevant departments to carry out joint law enforcement on the project and continue to pay attention to the trend of the project.

Round Bar Ferrule

and the subcontractor, Changchun Juyi Construction Engineering Co., Ltd., admitted their illegal acts, the detachment obtained the subcontractor’s enterprise business license and power of attorney according to law, inquired about the transcripts and on-site inspection records, and made administrative punishment decisions according to law, A fine of 300000 yuan shall be imposed on the construction unit for the illegal act of damaging and damaging drainage facilities.

in view of the illegal act of damaging and damaging drainage facilities in the construction of the project, the law enforcement personnel issued the decision on on on-site treatment measures according to law, ordered the construction unit to complete the rectification within 3 days and go to relevant departments for further treatment.

The drainage subcontractor is Changchun Juyi Construction Engineering Co., Ltd.

On August 24, when the rectification was ordered to expire, the law enforcement team of the municipal construction commission rechecked the matters involved.

It was found that there was still a large amount of sewage discharged into leijiagou, and the relevant units of the project failed to rectify as required.

The municipal construction market law enforcement and Supervision Detachment attached great importance to it, and the law enforcement personnel immediately went to the site to carry out law enforcement investigation.