Shaanxi: the bid winner of Linyou famensi expressway construction is released!

second: China Railway 14th Bureau Group Co., Ltd.

Construction of civil works of Shaanxi Linyou famensi Expressway PPP project I.

There are 2 tunnels, converted into double tunnels, with a total length of 10978.5m, accounting for 23.7% of the total length of the route.

The planned construction period is 1218 calendar days from the commencement date, and the construction site is located in Fufeng County, Baoji City.

lftj-3 bid first: China Railway 18th Bureau Group Co., Ltd Second place of the company: China Railway 20th Bureau Group Co., Ltd.

3.9268 million cubic meters of subgrade excavation and 168900 cubic meters of filling; 11 bridges (4739m); (hub) 2 interchanges; 126.6m/4 culverts; One overpass of 75m.

The planned construction period is 1218 calendar days from the commencement date, and the construction site is located in Linyou County, Baoji City.

II Winning information lftj-1 bid first: China Railway 19th Bureau Group Co., Ltd.

third: China Railway 18th Bureau Group Co., Ltd.

congratulations to the bid winner! For more bid winning information, please pay attention to the submission of “road and bridge network” (ID: zgluqiao): bianji@9to.com Information cooperation: qq1949195..

The standard of two-way four lane Expressway with design speed of 100km / h, integral subgrade width of 26.0m (bridge width of 25.5m) and separated subgrade width of 13.0m is adopted for the whole line, and the design load is highway – class I.

Bidding scope: subgrade works, bridge and culvert works, tunnel works, crossing works, subgrade slope greening, relevant ancillary works and defect liability repair.

The owner of the project is Shaanxi guanhuan Linfa Expressway Co., Ltd., and the construction funds come from self financing and loans, The tenderee is the construction general contracting Department of the consortium of guanhuan Linfa expressway project of China Railway Construction Investment Group Co., Ltd., and now the affiliated units of China railway construction are invited to participate in the bidding.

Shijiushan long tunnel and yeheshan extra long tunnel are set to cross two nature reserves, anshuzhuang and Yehe, and then pass through luma, Nanyang, Liucun and Xilong village to the south, It crosses the Guanzhong Ring Road on the west side of Jianhe village, crosses the proposed West France intercity railway to the south, crosses Xinyi reservoir after passing through Zhonghe village, passes Xiaoliu village to the south, and connects with the existing Jiang France Expressway on the west side of chopping village.

The total length of the route is 46.333km.

Lot lftj-2: the mileage range is K9 + 340 ~ K15 + 885, and the route length is 6.545km.

second: China Railway 20th Bureau Group Co., Ltd.

34.

Subgrade excavation is 5.4159 million cubic meters, filling is 578600 cubic meters, and there are 16 bridges of 4966.1 meters, including 1 super major bridge of 1207 meters, 12 major bridges of 3656.6 meters and 3 medium bridges of 102.5 meters, accounting for 20.8% of the line length; There are 2 tunnels of 10978.5m and 1 inclined shaft of 1530m, accounting for 46.0% of the line length; (hub) 2 interchanges and 1 overpass of 75m; The bridge tunnel ratio is 65.02%.

Bid section division, planned construction period and specific construction location: lftj-1 bid section: mileage range K0 + 000 ~ K9 + 340, and the route length is 9.395km.

Lifting Insert

The subgrade excavation of the whole line is 6.4559 million m3, the filling is 3.4369 million m3, and the spoil (including tunnel spoil) is 6.097 million m3.

There are 5 interchanges, 1 service area and 1 connecting line along the whole line, with a bridge tunnel ratio of 38.6%.

There are 30 bridges (including overpasses, the same below) on the main line, which are converted into full width bridges, totaling 6916.1m, accounting for 14.9% of the total length of the line.

Subgrade excavation of 150000 m3 and filling of 145000 m3; One 122.8m long bridge; 5824m / 1.5 tunnels.

Subgrade excavation is 134537m3 and filling is 2724900m3; 3 medium bridges of 222m; There are 5180m / 0.5 tunnels and 1530m / 1 inclined shaft.

Lftj-3 bid section: the mileage range is K15 + 885 ~ K23 + 823, and the route length is 7.938km.

Shiguxia hub interchange is set to connect with Xunyi Fengxiang Expressway under construction, and then lines are set along Chengshui River and Qishui River to the south.

lftj-2 bid first: China Railway 20th Bureau Group Co., Ltd.

Construction location and scale: the project starts from Laozhuang, Beihe County, in the east of Linyou county.

The planned construction period is 911 calendar days from the commencement date, and the construction site is located in Linyou County, Baoji City.

third place: China Railway 19th Bureau Group Co., Ltd.

This bidding is for the construction of civil works within K0 + 000-k23 + 823 of Shaanxi Linyou famensi expressway project, with a total length of 23.878km, including subgrade, bridge and culvert, tunnel, intersection works, subgrade slope greening and related ancillary works.

third: China Railway 14th Bureau Group Co., Ltd.

project overview bidding conditions: the bidding project Shaanxi Linyou famensi Expressway PPP project has been approved by Shaanxi development and Reform Commission in the form of sfgj [2020] No.