Shenyang Metro Line 1 East extension section II construction daily 2021 / 11 / 11

(8 operators) operation scenario:   ① Drilling construction of bored cast-in-place pile (b-219).

   ② The enclosure spray pipe is expanded outside the east side of Xinning Street station, and the threading pipe is removed.

  Reinforcement cage processing team: 7 operators.

  Enclosure pile construction team: 6 operators.

On November 11, 2021, the seventh day of October of the lunar calendar, the weather is cloudy, the temperature is 2 / – 14 ℃, and the southwest wind is level 2.

(4 operators)    ② Two bored cast-in-place piles (b-219, b-147) were completed today, with a total of 119 completed and 359 remaining.

(6 operators)    ③ Reinforcement cage processing.

Fixing Socket Waved End Nail Plate

Machinery and personnel allocation:   Temporary construction and civilized construction team: 12 operators.

(7 operators)   ④ Construction of the material shed of the reinforcement processing yard on the west side of Nissan and the expansion of the enclosure, spray pipe and threading pipe outside the yard on the east side of Xinning Street station.

Construction progress: Dongling road Xinning Street:   ① The civilized construction team shall scrub the enclosure and clean the site.

  On site mechanical equipment: 2 rotary drilling rigs, 1 cage roller, 2 hook machines and 4 cranes…