Shenyang Metro Line 1 East extension section II construction daily 2021 / 11 / 12

Construction progress: Dongling road Xinning Street:   ① The civilized construction team shall scrub the enclosure and clean the site.

  Enclosure pile construction team: 6 operators.

On November 12, 2021, the eighth day of October of the lunar calendar, the weather is fine, the temperature is 2 / – 10 ℃, and the south wind is level 1.

  ③ Reinforcement cage processing.

(4 operators)    ② Three bored cast-in-place piles (b-216, b-149, b-145) were completed today, with a total of 122 completed and 356 remaining.

(7 operators)   ④ The temporary construction team constructs the material shed of the reinforcement processing yard in the west of Nissan.

  On site mechanical equipment: 2 rotary drilling rigs, 1 cage roller, 2 hook machines and 4 cranes…

(6 operators)    ③ Reinforcement cage processing.

   ② Clean the site for civilized construction.

Lifting Eye

Machinery and personnel allocation:   Temporary construction and civilized construction team: 12 operators.

  Reinforcement cage processing team: 7 operators.

(8 operators) operation scenario:   ① Drilling construction of bored cast-in-place pile (b-145).