Single choice questions of building decoration and decoration engineering construction

Relative to (), the corresponding cost item in construction cost planning is the actual value.

During the dynamic tracking and control of the construction progress objectives of the project, the progress control cycle shall be () as appropriate.

C.

Implement laws, regulations and policies B.

B.

completion acceptance or payment of project funds shall not be carried out without the signature of the supervising engineer.

The project manager is the representative of the legal representative of the enterprise on the project.

sign construction contract C.

select construction team correct answer: D   My answer: D score:   10.0:4 in order to catch up with the construction period, the project manager of a construction enterprise did not strictly control the construction quality, resulting in the rework of a subdivisional project, resulting in certain economic losses to the construction project.

Project management planning outline B, construction contract C, construction organization design document D, characteristics of the project correct answer: C   My answer: a score:   0.0 points 1.

A.

A.

as long as the project objectives cannot be achieved, the project objectives can be adjusted.

1、 Single choice question (8 questions in total, 80.0 points) 1 a construction enterprise has undertaken a construction task.

A.

Collect the actual value of construction cost according to the schedule control requirements B.

Adjust the project objective B, take corrective measures to correct the deviation C, collect the actual value of the project progress D, compare the actual value of the project objective with the planned value correct answer: C   My answer: C score:   10.0.8 a construction enterprise contracted a residential building construction project, determined the planned commencement date and completion date of the project, and further determined the section construction period target and monthly planned construction period of main divisional and subdivisional works.

Construction materials, components, fittings and equipment shall not be used or installed in the project without the signature of the supervising engineer.

A.

The project manager used the dynamic control principle to control the construction progress.

B.

find out the deviation and take corrective measures C.

Correct answer: D   My answer: D score:   10.0 points 2 according to the relevant regulations of China, the following statement about the project manager is correct ().

The first step is ().

The core content of dynamic control is to determine the project target value.

the responsibility and authority of the project manager shall be determined by the parties to the project contract   My answer: a score:   10.0 sub 3 in the process of undertaking the management of project construction, the project manager shall sign the project contract with the legal representative of the enterprise according to the project contract signed between the construction enterprise and the construction unit, and the management power of driving is () within the scope of authorization of the legal representative of the enterprise.

A.

D.

In order to timely understand the profit and loss of the construction project during construction cost control, the cost item that needs to be compared with the actual construction cost is ().

Correct answer: B   My answer: B score:   10.0 points 5 according to the code for construction project management (GB / t50326-2017), the authority that the construction project manager can exercise is ().

Fixing Socket Waved End

① ② ③ ④ B, ① ④ ② ③ C, ④ ① ② ③ D, ④ ① ③ ② correct answer: B   My answer: B score:   12.5 points 2 if the probability of occurrence of the risk of rising material price of a project is estimated to be 2 and the loss caused by the risk is 3, the risk level shall be rated as () level.

1 year B, 1 week C, 1 month D, half a year correct answer: B   My answer: B score:   10.0 points 6 a construction enterprise signed a project construction contract, which defined the construction period objectives of the project.

Organizational measures B, management measures C, technical measures D, economic measures correct answer: a   My answer: a score:   10.0:5 a construction enterprise undertook the construction task of a major project, which has tight construction period and complex technology.

Ⅰ B, Ⅱ C, Ⅲ D, Ⅳ correct answer: B   My answer: B score:   12.5 score 3: the risk level is high, the risk consequences are serious, and may cause damage or casualties in a large range.

the candidate confirmed by the project manager for the parties to the contract shall not be replaced.

Single choice questions (4 questions in total, 50.0 points) 1 when a construction unit carries out risk management for the project, the main management links determined include: ① risk identification; ② Risk response; ③ Risk control; ④ Risk assessment.

The replacement of the technical director of the construction unit must be approved by the chief supervising engineer.

A.

Investigate legal responsibility B, investigate economic responsibility C, investigate social responsibility D, cancel the qualification of constructor.

Correct answer: C   My answer: C score:   10.0 points 7 in order to dynamically track and control the project objectives, the first thing to do in the construction process after determining the planned value of the project objectives is ().

A.

B.

regularly compare the planned value and actual value of construction schedule.

Actual construction cost B, project contract price C, final settlement price D, project settlement payment correct answer: B   My answer: B score:   10.0 points 3 the correct statement about the dynamic control of project objectives is ().

A.

One B, two C, three D, four correct answer: B   My answer: B score:   12.5 points 4 in the regional division of event risk, once a risk event occurs, it will cause significant losses, but the probability of occurrence is very small ().

C.

organize project completion acceptance D.

The treatment of the project manager by the construction enterprise is mainly ().

Risk area AB, risk area BC, risk area CD, risk area D correct answer: B   My answer: B score:   12.5 points     1、 Single choice question (6 questions in total, 49.8 points) 1 the regulations on the quality management of construction projects stipulates that the project supervision unit shall bear the supervision responsibility for the construction quality.

dynamic control is divided into prior control and process control.

In this regard, the following options, except (), are the legal functions and powers of the project supervisor.

A.

A.

This risk belongs to level () risk.

A.

establish various professional management systems and organize the implementation of correct answer: C   My answer: C score:   10.0 point 6 the following is wrong about the preparation basis of project management responsibility statement ().

A.

Single choice questions (6 questions in total, 60.0 points) 1.

Correct answer: C   My answer: C score:   8.3 points 2 in the process of supervision, if the supervising engineer finds that the engineering design does not meet the design standards of building engineering, he shall ()..

determine the supplier of bulk resources C.

Deviation value B, adjustment value C, planned value D, actual value correct answer: C   My answer: C score:   10.0 tasks and responsibilities of the construction project manager 1.

preside over the work of construction project management department D.

construction shall not enter the next process without the signature of the supervising engineer.

Then the following processes are sorted correctly as ().

the task of the project manager is limited to presiding over the project management.

The purpose is to determine the parameters used for target control ().

C.

A.

A.

A.

A.

A.

The dynamic control of project objectives is the most basic methodology of project management.

D.

Corresponding cost item in construction cost planning B, corresponding cost item in project contract price C, corresponding cost item in project bid price D, corresponding cost item in project payment correct answer: B   My answer: B score:   10.0 point 2 the planned value and actual value of construction cost are relative.

Organize or participate in the evaluation of project management performance B.

Those who bear the overall management responsibility for the construction of the project are () a, the project Department of the construction unit B, the legal representative of the construction enterprise C, the chief supervision Engineer D and the construction project manager.

Correct answer: C   My answer: C score:   10.0 points: 4 adjust the responsibilities of project management personnel and clarify various management work processes, which belong to the dynamic control and correction measures of project objectives ().

A.

D.

decompose the construction schedule objectives layer by layer D.