The special construction scheme that does not require expert demonstration shall be submitted to the supervision unit after being reviewed and qualified by the construction unit, reviewed and signed by the chief supervision engineer of the project, and reported to the project legal person for the record.
The qualified ones shall be signed and confirmed by the technical director of the construction unit.
In case of subcontracting, the general contractor and the technical director of the subcontractor shall jointly sign for confirmation.
Clause 7.3.8 The construction unit shall modify and improve the special construction scheme according to the review and demonstration report, and organize the implementation only after it is reviewed and signed by the technical director of the construction unit, the chief supervision engineer and the person in charge of the project legal entity…
Article 7.3.3 of guidelines for construction safety management of water resources and hydropower projects (sl721-2015) The special construction scheme shall be reviewed by the professional technicians of the construction technology, safety, quality and other departments organized by the technical director of the construction unit.
The approval of the special construction scheme does not comply with Article 26 of the regulations on the administration of work safety of construction projects (Order No.
393 of the State Council) The construction unit shall prepare safety technical measures and temporary power consumption scheme on the construction site in the construction organization design, prepare special construction scheme for the following divisional and subdivisional works with high risk of reaching a certain scale, and attach safety checking calculation results, which shall be implemented after being signed by the technical director and chief supervision Engineer of the construction unit, On site supervision shall be carried out by full-time safety production management personnel…