After the removal of all the middle span beams, after two months of careful preparation, the beam removal of the East and West spans of Xinhua bridge was fully launched on October 29.
At the south of the intersection of Xinhua West Road and Renmin Road, vehicles from the railway station to the central square need to bypass Jianshe Road due to the construction of Xinhua bridge project and other construction.
It is expected to complete the demolition of the east side beam before November 22, The demolition of the beam body on the west side shall be completed before December 18.
On October 28, Lusong Traffic Police Brigade announced that due to the needs of Xinhua bridge construction, traffic control will be implemented on the intersection of Xinhua West Road and Renmin Road.
Zhuzhou news network and palm Zhuzhou have been included in the list of Internet news information release source units.
on the 29th, the demolition of the No.
Source: Zhuzhou daily editor: Zhang Yuxiao reviewed by: Luo Xiaoling Luo Chunjiao, attention! There are 16 new e-police in Zhuzhou City, which are distributed here…
Lushong traffic police reminded drivers that during the closed construction period, passing vehicles and pedestrians should choose other travel routes in advance, reasonably arrange travel time, obey the command of the on-site traffic police, and do not go to the scene to watch.
3 T-beam of the second span of Xinhua bridge was successfully removed.
During beam transportation and disassembly, the road at the intersection of Xinhua West Road and Renmin Road shall be temporarily occupied.
According to the construction period plan, the demolition of the bridge deck will be completed on December 18.
3 T-beam within the specified time.
3 T-beam of the second span on the west side of Xinhua bridge was officially started.
Therefore, the traffic at the intersection will be closed from 12:00 to 14:30 every day for a total of 40 days from October 29 to December 18, according to the construction needs, so as to remove and break the beam body.
3 T-beam of the second span on the west side of Xinhua bridge was successfully removed.
At present, the demolition and reconstruction project of Xinhua bridge is in progress, and the demolition of the beam body of the West 1# span will be carried out soon.
From “fried meat with pepper” to “fried pepper with meat”, why is the price of vegetables in Zhuzhou more expensive than meat?..
Yuan Zhulin introduced that the new Xinhua bridge needs 36 beams, and 24 have been made at present.
The No.
On October 29, the No.
Yuan Zhulin, Secretary of the joint party branch of the demolition and Reconstruction Project Department of Xinhua bridge, introduced that there are 19 T-beams in the East and West spans of Xinhua bridge.
Reporter / Liu Zhen photographed at 11:50 a.m.
Vehicles from Wangfujing turn around near the intersection of Xinhua West Road and Renmin Road.
According to the construction plan, the West span will use the skylight point at noon every day to dismantle one T-beam in two days, and the East span will use the characteristics of night shutdown of intercity railway to dismantle one T-beam in one day.
If you need to turn left from Xinhua Road to Renmin Road, you can turn left at the intersection during non construction time.
The intersection of Xinhua West Road and Renmin Road was closed at noon.
Please bypass during the construction period.
More than 200 workers on the site cooperated with bridge erecting machines, cranes and other heavy machinery to successfully lift the No.
Reporter / Liu Zhen photographed that while the old bridge body was demolished, the pouring and prefabrication of the new bridge body was under way.
After being transported to the other side by flat car, it was broken and disassembled in situ.