Everyone knows that the oil price is so expensive now.
If it exceeds the scope, it is necessary to sign the transportation distance.
If the negotiation fails, it will ask Party A for a visa and withhold its project funds.
The pump shift is not cheap, so the pump model should be written.
During foundation construction, brick formwork is used in response to Party A’s requirements to speed up the progress or considering the need for early backfilling due to slope instability.
If there are underground obstacles, it should be verified.
The roof is often changed by Party A.
If there is no requirement at the time of bidding, it can also be signed, and the price of brick formwork is higher than that of formwork erection.
If water seepage is seen in excavation, the height of underground water level can be verified.
The earthwork transportation distance naturally depends on whether it is beneficial.
It must be remembered that the visa should not be delayed until the commencement, and it should be done at least once a month, which is also the principle of long-term visa.
When these leaders who like to change invented a new roof practice, it will look good to recalculate the unit price.
Finished product protection finished product protection is not innate.
The copyright belongs to the original author and the company.
Welcome to buddy group to exchange learning official account.
In addition to making records of concealed works, the pile foundation should also pay attention to the visa of underground obstacles.
These can’t be verified afterwards.
The most common occurrence of masonry in masonry is to dismantle and dismantle the masonry.
5.
The price of wet soil is higher than that of dry soil, and the sludge will be higher.
If you need information about real estate development and construction engineering, you can leave a message.
If it is required to mention it in the contract, the additional requirements will be paid.
2.
You should give as much as you sign.
Some list measures are not clearly listed, causing trouble in subsequent settlement.
2.
If the foundation construction is stopped or delayed, it should be signed.
Some articles come from the network and are sorted by us.
The construction unit shall be responsible for the three supplies and one leveling of the site.
Some things are unreasonable.
6.
3.
It’s not that you have finished product protection of marble when you shop marble, but that you have done finished product protection seriously.
The template is solved by one item.
If sufficient backfill soil cannot be stacked on site under the condition of narrow site or unstable slope, the outward earthwork volume and transportation distance shall be signed.
If Party B also participates in the work, it can negotiate with Party A.
The calculation in this is quite complex.
Pile foundation part 1.
Because most of the bids consider the on-site stacking of soil, and the remaining soil is transported out.
At the same time, it also reminds us: 1) if Party A does not agree on the progress or the agreement is not detailed enough, it can delay the work as much as possible to strive for claims in its own favor.
If you can’t get the well point, you should strive for pump dewatering.
A complete set of information disclaimer of real estate engineering: this number is committed to the promotion of good articles.
2) If there is a construction period requirement during the construction, check it first.
The only thing to pay attention to is that overtime also increases a series of efficiency reduction expenses such as machinery operation salary.
3) During the construction, Party A has no right to add terms, saying that the top can not be closed for a few months and days, and how much penalty will be imposed for a day’s delay.
2.
For the template added by rush work, it is a fair and aboveboard rush work fee, but in fact, everyone didn’t want it.
It is strictly prohibited to be used for commercial purposes and personal communication by fans, If you are not concerned with the official account, please contact us if you want to discuss copyright issues..
It is no problem to dismantle the wall, but the visa must explain the damage degree of the brick (otherwise the audit will directly reduce the materials for you).
Although you don’t have much money, it’s not cost-effective to be cut down.
The cost of clearing underground obstacles is not cheap.
Now many projects are priced by list.
It is recommended to refer to relevant publications for more understanding.
Real estate engineering concerns Earth rock part of real estate engineering circle 1.
However, if the subcontractor damages or pollutes your things, it will not ask him for it.
Cooperation fee didn’t expect that the cooperation fee can also be visa, right? The cooperation fee is only that you provide water supply, electricity, scaffold, vertical transportation and other cooperation for other subcontractors to complete their processes (note that the water and electricity fee is not included in the cooperation fee, depending on how agreed in the contract).
If the excavated soil is transported away and backfilled, it will not be counted as money if the cost is not signed.
Therefore, the visa added in the template is particularly important.
The drainage in the quota only discharges surface water and a small amount of open water.
Otherwise, due to a long time, the supervisor of Party A cannot assess, and it will be troublesome to supplement the signature in the later stage.
If it encounters rock, it should sign the rock depth in time.
If it is not specified, it is likely to be cut directly for you.
Of course, if the work is suspended for a long time, it must be recorded.
If the damage is not serious, the loss rate and secondary use of the brick can be signed to remove ash scars and slag, etc.
Note that when calculating the unit price, do not forget the exhaust pipe and pipe fittings of the insulation layer, the oil impregnated wood wool board and ointment caulking of the surface protective layer.
If the conditions are not enough, don’t fool around with a small sump and go through the gang carefully.
Although it can be argued, it is always good to do things ahead.
Template part 1.
Precipitation and drainage 1.
if you master the know-how, you can cut in at a low price during bidding.
During the foundation construction period, if the construction period is suspended due to rain or delayed due to Party A, the drainage and precipitation expenses can be signed according to the unit shift.
If it is enough for visa, it’s good to form a habit.
If it does not exceed the scope of the list, it is OK.
Underground water is not considered in earthwork bidding.
The real estate industry circle introduces real estate engineering circle for real estate engineering industry information, including industry research report, enterprise management, project pre stage, marketing plan, design information, cost information, contract, budget cost, finance, construction, engineering, sale, latest information sharing platform, and continuously update the latest real estate information.
The concealed records shall also be as detailed as possible, that is, at least: hole depth, pile length, reinforcement cage length, empty section length, pile diameter and rock entry depth.
Vertical transportation is similar to the formwork part.
Even if you take a penny around the scene and spread a broken sack, you should prove it as soon as possible.
4.
The content is only for learning and communication.
If a large amount of drainage or quicksand treatment, it can be signed.
Pay attention to the well point.
According to the legal construction period or the bidding construction period, the speed required by Party A now leads to the increase of the number of sets of templates.
2.
In addition, if the water seepage is large, the construction scheme can also be prepared to apply for drainage and dewatering measures and slope support measures.