2) Whether the quantity, specification and performance of the Contractor’s mobilized construction equipment meet the provisions of the construction contract, and whether the mobilization situation and plan meet the needs of commencement and construction progress.
It can be issued only after meeting the opening conditions.
provided by the employer as agreed in the construction contract.
Commencement of contract works (1) the supervision organization shall issue the commencement notice to the contractor with the consent of the employer, and the commencement date shall be specified in the commencement notice.
(3) After completing the preparation for commencement of the contract project, the Contractor shall submit the application form for commencement of the contract project to the supervision organization.
4) Provision of roads, power supply, water supply, communication and other conditions and resources for which the employer is responsible as agreed in the construction contract.
If the project fails to start on schedule due to the contractor, the supervision organization shall notify the contractor to submit a written report according to the construction contract, explaining the reasons for the delay in starting and the measures to speed up the construction.
After the above conditions are met, the supervision organization shall reply the Contractor’s application for commencement of the contract project.
The concrete pouring and opening supervision organization shall examine and approve the concrete pouring and opening report form submitted by the contractor.
4.
The supervision organization shall check that all conditions for commencement are met.
12) The commencement application report of the contract project submitted by the contractor after the completion of construction preparation.
3) Provision of construction land.
If the project fails to start due to the employer, the supervision organization shall timely negotiate with the employer and the contractor on remedies after receiving the Contractor’s request for extension of construction period.
Click the text above to pay attention to the commencement of our water conservancy projects, generally including the commencement of contract works, divisional works, unit works and concrete pouring and warehouse opening.
11) Construction process test and stockyard planning to be carried out in accordance with the provisions of the construction contract and the requirements of the construction drawings.
2.
Commencement of unit works: the first unit works shall be started after the commencement approval of divisional works, and the subsequent unit works can be started only with the construction quality qualification document of the previous unit signed by the supervising engineer.
2) Handover of survey datum points.
(4) The commencement conditions that the employer must meet are: 1) provision of construction drawings of the first batch of commencement projects.
Long press to identify and scan the QR code..
4) Whether the testing conditions of the contractor or the entrusted testing organization comply with the provisions of the construction contract and relevant regulations.
5) The Contractor shall review the survey datum points provided by the employer, and complete the layout of construction survey control network and the mapping of original topographic map of construction area on this basis.
7) The Contractor’s quality assurance system.
6) Sand and gravel system, concrete mixing system or commercial concrete supply scheme, as well as the preparation of on-site roads, water supply, power supply, air supply and other auxiliary processing plants and facilities.
Commencement of divisional works before the commencement of divisional works, the Contractor shall submit the commencement application form of divisional works to the supervision organization, and the commencement can be carried out only after being approved by the supervision organization.
(5) The Contractor’s construction preparation meeting the commencement requirements includes the following contents: 1) whether the main management personnel, technicians and special operation personnel dispatched by the contractor are consistent with the construction contract documents.
(2) The supervision organization shall assist the employer in handing over to the contractor the construction land, roads, survey datum points, water supply, power supply, communication, etc.
Next, let’s take a closer look.
8) Safety production management organization and safety measures documents of the contractor.
1.
10) Construction drawings and technical documents provided by the contractor.
In case of any change, it shall be re examined and reported to the employer for approval.
3) Whether the quality and specifications of the mobilized raw materials, intermediate products and engineering equipment comply with the construction contract, and whether the storage capacity and supply plan of raw materials meet the needs of commencement and construction progress.
3.
Before the commencement of water conservancy projects, the construction parties must meet the corresponding conditions before they can start.
9) Construction organization design, special construction scheme, construction measure plan, general construction schedule, capital flow plan, safety technical measures, flood control scheme and disaster emergency plan submitted by the contractor.