Construction daily of electromechanical work area III of Hangzhou Metro Line 10

Decoration: stone paving of outdoor cooling tower.

International Convention and Exhibition Center Station: electromechanical team: long channel lamps, suspenders, bridge covers in public areas; Inlet and outlet water pipe insulation, cooling tower water pipe installation.

Xinxing Road Station: electromechanical team: install the bridge cover plate for the piston air duct at end B, replace the fan nut in the environmental control room at end B, rectify the air duct fireproof board in the environmental control room at end a, replace the fan nut in the environmental control room at end a, install the refrigerant pipe bridge in the exhaust duct, and clean the main waste sump.

Safety production on the working face of each work point of the project, and water pipe insulation of long channel at the entrance and exit of International Exhibition station B.

Er Hang Road Station —— 1 air pipe ㎡ 1300000400400100.00% 130002 ceiling ceiling m296003 enamel steel plate wall m26800006885685100.00% 68004 marble floor ㎡ 98000910910910910100.00% 9800 Mr.

4.

3.

Daily report on construction of mechanical and electrical work area III of Hangzhou Metro Line 10 Monday, January 3, 2022, weather: sunny, temperature 4-14 ℃ (I) completion of output value (10000 yuan) 1 planned day completion date completion of per capita output value weekly planned completion ratio of weekly planned completion ratio of 000000 February planned month completion ratio of annual planned year cumulative annual completion ratio of 0001520015200100.00% 2 Completion of construction progress No.

project unit design quantity day plan date completion month plan month completion proportion of completion month of one country exhibition station ——– 1 wiring m270000002197100.00% 270002 line pipe m196500030273027307100.00% 196503 marble ㎡ 43000017551755100.00% 43004 enamel steel plate ㎡ 228700907907100.00% 22875 lamp sets 63700487487100.00% 6376 ceiling ceiling ㎡ 540000484048 40100.00% 5400 Mr.

8 water pipe insulation ㎡ 3854002114100.00% 3854 Mr.

3、 Construction operation management personnel and equipment input No.

2 air Pavilion excavator excavates pipe trench.

2.

5 water pipe insulation m23854001514100.00% 38 54.

Hanghang Road Station: sludge cleaning of the main waste water pump room, garbage cleaning from the wall ditch, edge closing of the toilet, edge closing of the enamel steel plate at the entrance and exit, sanitary cleaning in the station, thermal insulation of the air shaft at end B and its environmental control room, and the air duct at end a is wrapped with fireproof board; Fire blocking of equipment area.

5.

The drainage pipe at the entrance and exit of Wujia Road B has been changed according to the new drawing, and the construction has been completed.

Other matters 1.

Rectification of acceptance problems and cleaning.

Decoration team: replace the sound-absorbing board on the wall of the make-up fan room at end B.

Decoration team: Construction of dust stop belt for disabled ramp.

Spread Anchor

Repair and polish the wall of equipment area corridor at end a of Xinxing road..

project construction personnel (person) management personnel (person) equipment input I Xinxing Road Station – 1 electromechanical team day shift: 8 person day shift: 2 person electric drills 4 sets, 2 electric welding machines 2 decoration team day shift: 7 person day shift: 2 person Wujia Road Station – 1 electromechanical team day shift: 6 person day shift: 2 person electric drills 2 sets 2 electric welding machines, 2 decoration team day shift: 3 people day shift: 2 people, 3 International Convention and Exhibition Center Station — 1 electromechanical team day shift: 16 people day shift: 2 cutting machines, 2 electric drills, 2 electric welding machines, 2 decoration team day shift: 10 people day shift: 2 electric tricycles, 1 angle grinder, sixiangyuan Road Station — 1 electromechanical team day shift: 3 people day shift: 2 cutting machines, 2 electric drills 2 electric welding machines, 2 decoration team day shift: 6 people day shift: 2 people, WuHangXing Road Station – 1 electromechanical team day shift: 13 people day shift: 2 cutting machines, 2 electric drills, 1 electric welding machine and 1 forklift, 2 decoration team day shift: 14 people day shift: 2 people, 4.

7 cable ㎡ 120000014301430100.00% 12000 Mr.

No.

Xiangyuan Road Station: stainless steel railings, glass gluing and fireproof blocking; Glue the glass of steel structure canopy at the entrance and exit, glue the gap of dry hanging aluminum plate on the side wall of sunken square at entrance and exit a of Xiangyuan Road station, and construct the railing foundation of multi online outdoor unit (the materials have not arrived).

Wujia Road Station: electromechanical team: water collecting well cleaning.