Construction organization -85- resource assurance measures for battery production project

Solar power stations, solar water heaters, electric vehicles and energy storage power stations are all based on the mass production of batteries, and solar cell production is the demand side of purification projects.

Our company has more than 20 professional companies, including all disciplines of engineering construction, which can fully meet the needs of the project.

With the completion of the key dates of each stage of the project, the labor costs of the construction team shall be paid in time, which can not only fully mobilize their enthusiasm, but also ensure that each labor operation team arranges sufficient operators during winter and Spring Festival.

Negotiate with each material supplier in advance to ensure the supply of materials during holidays, and reserve materials for at least 20d.

During holidays, our company will strengthen the on-site construction management from the aspects of human, material and financial resources, adopt the effective method of management personnel rotation and operator rotation, and continuously organize the construction, so as to ensure the realization of the construction period goal of the project.

(2) the construction team with good reputation and high quality is one of the basic conditions to ensure the completion of the project on schedule.

Magnetic Recess Former

During holidays, the project management department will increase subsidies for project construction personnel and adopt the method of daily subsidies and awards.

Thank # warm Meng for pursuing excellence and Zhai Lijuan for sharing the materials.

The project content constructed by our company shall be constructed by our own branch.

5.2.2 resource assurance measures ⑴ we have a branch in XX to make full use of the social resources we have established in XX.

Send personnel to visit the families of construction workers during the festival to stabilize the thoughts of construction workers and enhance cohesion, More contents: 1 – project overview 2 – wastewater treatment station 3 – bulk gas station 4 – construction objectives 5 – high altitude operation 6 – overall arrangement of project implementation 7 – arrangement of construction team 8 – main construction stage 9 – construction method of divisional and subdivisional works 10 – elevation measurement control 11 – settlement observation 12 – installation of embedded anchor bolts 13 – Determination of bolt position 14 – formwork removal Concrete curing 15 – Super leveling professional construction 16 – floor construction process 17 – cover and protect with film 18 – formwork installation 19 – concrete pouring 20 – concrete surface treatment 21 – steel structure fabrication 22 – detail design 23 – connection node design 24 – steel structure fabrication process 25 – steel structure processing and fabrication process 26 – setting out Allowable deviation of template 27 allowable deviation of steel after correction 28 cutting 29 allowable deviation of sawing 30 allowable deviation of refined bolt hole 32 allowable deviation of bolt hole spacing 33 assembly principle 34 principle of steel plate splicing 35 allowable deviation of welding structure assembly 36 H-section steel assembly 37 welding H-section steel column fabrication 38 welding process flow chart of steel structure 40 welding rod Table 41 – General Provisions for welding flux selection 42 – submerged arc welding 43 – CO2 gas shielded welding 44 – carbon arc gouging 45 – welding sequence 46 – member derusting method and inspection standard 47 – steel member coating method 48 – derusting and repair of coating defects 49 – Parts prohibited from painting 50 – protection and transportation of finished products 51 – steel structure installation 52 – hoisting of steel columns 53 – roof truss installation and construction 54 – high strength bolt installation 55 – profiled roof panel installation 5 6 – positioning of fixed support 57 – Installation precautions 58 – Installation of sandwich color plate wallboard 59 – fire retardant coating of steel structure 60 – binding of beam and plate reinforcement 61 – binding of column reinforcement 62 – column formwork 63 – beam and plate formwork 64 – stair formwork 65 – precautions for construction of wood plywood formwork 66 – concrete engineering 67 – beam Slab concrete 68 – concrete curing 69 – masonry construction 70 – roof waterproof construction 71 – plastering construction 72 – emulsion paint wall construction 73 – ceiling construction 74 – penetration crystallization wear-resistant floor construction 75 – floor tile floor construction 76 – epoxy floor construction 77 – rolling shutter door installation 78 – aluminum alloy window installation 79 – water supply pipe installation 80 – drainage pipe installation 81 – electrical piping and threading in pipe 82 – lightning protection and grounding works 83 – construction schedule Draw 84 – construction progress control flow chart 85 – resource assurance measures recognition and implementation of group regulations.

① Before festivals and holidays, organize mobilization and arrange construction projects.

(4) fully mobilize the enthusiasm of employees, carry out labor competition, set off a climax of big work, praise and reward those who have completed the plan, and criticize and punish those who have not completed the plan.

Welcome to “purify four groups and follow the regulations” (open the link to see details)..

(3) the system of special funds for the project shall be implemented to avoid affecting the project progress due to capital problems during construction, and fully ensure the allocation of labor and machinery and the timely mobilization of materials.

The labor force shall take turns and vacations at ordinary times to ensure that the attendance rate on holidays is not less than 90%, and “attendance guarantee” shall be carried out at the same time to ensure the labor force required for the project.

Therefore, starting today, I will share the construction organization design of solar cell production projects with you.

(5) measures to ensure the construction period during holidays.

For each work quantity completed in a fixed work day, a subsidy of 30 yuan and a reward of 20 yuan will be given to mobilize the enthusiasm of construction personnel, Ensure the normal construction of the project.

② In order to ensure the quantity and construction quality of construction personnel on holidays, sign reasonable construction contracts with the construction team and formulate reward and punishment system.

At the same time, the special fund system also provides a reliable fund guarantee for the project department.

Reserve all kinds of vulnerable mechanical parts in advance to ensure the normal operation of the machinery.

We are familiar with XX’s certificate handling process and have long-term contact with relevant government engineering construction departments, which can avoid the impact of certificate handling on the construction period of the project.