How to construct clean room project? Whole process demonstration!

Wood frame products are not allowed, and the finished products shall not have pungent taste.

Components and materials of purified air conditioning system (1) the internal surface and built-in parts of purified air conditioning unit shall be made of material surface resistant to disinfectant corrosion, and the material surface shall be smooth.

(2) All door jambs are made of stainless steel.

(4) Differential pressure gauge shall be set before and after all levels of air filters in the unit, and the measuring connecting pipe shall be unobstructed and installed tightly.

It must have the following functions: A.

(2) The clean outer corridor and other auxiliary rooms shall be made of color steel plate, and the thickness of color steel plate must be in accordance with national standards.

various medical gas alarms J.

2.

(7) Combined power socket each operating room is equipped with 10 universal sockets and 2 grounding terminals.

Basic operation configuration (1) the basic equipment of each clean operating room meets the following requirements.

The height of the upper edge of the return air outlet opening shall not exceed 0.5m above and below the ground, and the lower edge of the hole shall not be less than 0.1M from the ground.

The multi-functional control system must centrally control all systems in the operating room, and the opening key shall be plane touch type.

3.

(8) The main materials of all equipment are made of imported frosted stainless steel, and the quality requirements meet the standards.

Door (1) a light control induction electric door is designed for the entrance door of the operating department, the operating room door and the workshop door.

5.

(2) The coiled material joints are welded by hot welding, flat and seamless, and are connected with the wall by circular arc.

Configuration requirements of purification air conditioning unit (1) imported parts are used to assemble medical sanitary purification air conditioning unit in operating room, clean corridor and auxiliary room, equipped with humidifier and dry steam device.

(2) Ten thousand operating rooms are one driven by three.

Air distribution (1) the air supply outlet in the clean operating room shall be centrally arranged above the operating table so that the operating table and its surrounding area are located in the mainstream area formed by the clean air flow.

(9) The wash basin is made of stainless steel; Each wash basin is equipped with a 60L electric water heater, equipped with sensing water nozzle, sensing soap, independent mirror lamp, and 12 sensing water nozzles.

(3) The condensate outlet of the surface cooler shall be equipped with a device that can automatically prevent backsuction and discharge condensate smoothly under negative pressure.

3.

high efficiency filter discharge system switch and fault alarm h.

4.

fire prevention alarm I.

communication system: between operating room and nurse station or other operating rooms The height of the embedded air interphone (1.2m from the lower part of the surgical anesthesia panel) shall be set at the height of 1.2m.

Ceiling (1) the designed ceiling height of the operating room is 2800mm, and the material of the operating room (except the debridement room) is the same as that of the wall.

temperature, humidity and regulation control of purification air conditioning system D.

Other doors of the operating department are designed with an electric door.

air handling system switch and operation status display E.

The condensate pipe cannot be directly connected with the sewer pipe.

(2) The designed ceiling height of corridor and auxiliary room is 2800mm, and the color steel plate ceiling is adopted.

lighting system switch F.

(6) The infusion guide rail shall be made of ceiling type, located on the ceiling above the operating table, parallel to the long side of the operating table, with a length of more than 2.5m, and the distance between the two rails shall be 1.2m.

(4) The corridor is provided with anti-collision handrails.

Design requirements for purified air conditioner 1 The purified air conditioning system shall keep the clean operating department under control, which can not only ensure the overall control of the clean operating department, but also enable the flexible use of each clean operating room.

Flat Rubber Recess Former

(3) The fresh air system adopts zoning centralized control and is equipped with a group of fresh air units.

3.

The purified air conditioning system shall be set separately from the auxiliary room, and the design parameters shall comply with the provisions of the construction standard of hospital clean operating department.

timer C.

3.

clock B.

4.

(2) The operating room must have a multifunctional control system.

(5) The materials of muffler silencing parts shall be resistant to corrosion, moisture absorption, dust accumulation and dust production.

2 electrical design requirements 1 The power distribution load of each operating room shall not be less than 8KVA.

2.

4.

(5) The drug cabinet, instrument cabinet and anesthesia cabinet shall be embedded in a convenient position.

2.

Glass fiber and its products are not allowed to be used as filling materials.

detailed explanation of the purification design requirements of the hospital clean operating room, comprehensive and detailed.

operating room shadowless lamp switch and light regulation g.

The average illumination of auxiliary rooms and corridors shall be above 200lex.

(4) The clean corridor of aseptic auxiliary room is provided with upper air supply and lower return air, and high-efficiency air supply outlet.

I.

(5) The clean corridor adopts high-efficiency air supply outlet for air supply and return.

Decoration requirements for clean operation Department 1 The wall of the operating department (1) the wall body of the operating room and the clean inner corridor is made of metal materials (electrolytic metal plate or color steel plate) with rust prevention, scrub resistance, acid and alkali resistance, fire prevention, sound insulation and heat preservation, and the wall connection is in the form of arc.

(2) The internal structure shall be easy to clean, and the cleaning wastewater can be discharged smoothly, which is not easy to form dust and breed bacteria.

(3) The doors of relevant auxiliary rooms shall be manual doors.

5.

Each operating room is equipped with 380V power supply (single socket is not allowed in the operating room).

(4) The embedded film viewing lamp shall be set on the wall opposite to the operator.

(2) The clean operating room adopts aluminum alloy plastic spraying ceiling air supply device for air supply, and the size of the air supply device shall not be less than Class 100 2.4 * 2.6 and class 10000 1.4 * 2.6 respectively.

1.

The design average illuminance of the operating department shall be above 400lex.

The floor (1) of the operation Department is made of anti-static, antibacterial, fireproof and wear-resistant PVC coiled materials.

(3) The clean operating room shall adopt the lower return air on both sides.

The lighting in the operating room is composed of clean gas sealed lighting panel, which is prohibited to be replaced by ordinary lighting panel, and the lighting adopts multi-point control.

The air supply is mandatory and should be controlled by the constant air volume valve..

(6) The filters at all levels in the purified air conditioner shall be primary type, and the final filter shall be made of materials that do not absorb moisture and grow bacteria.

Configuration requirements for purification system (1) clean the fresh air of the air conditioning system.