The site, paint and diluent shall be stored safely and well protected, and shall be isolated from heat source and fire source.
There is no adjustment in the final settlement of the area, and it is calculated according to the total square above.
1.
IV.
2.
The construction party shall guarantee the quality of the contracted project, and shall fulfill the responsibility and obligation of 5-year warranty and maintenance under the condition of no natural disaster, force majeure or human action.
the contract construction period 1.
The total calendar days of the contract construction period shall be days.
VIII.
In case of contact list and process change during construction, the increase and decrease of quantities and expenses will not be adjusted, Party A will not make compensation within the total price, and Party B shall be responsible for the win and loss.
2) in the process of project construction, the safety in production must be considered to alert the construction personnel to the safety in operation, such as the stability of grid rack, the pulling and exposure of wires, the placement of temporary contact equipment and tools, and the scope of activities during construction; Always remember “safety first and production second”, and do not force and risk construction in order to catch time and catch up with progress, regardless of safety.
3) during construction, construction workers must be equipped with safety settings and protective tools, such as safety belts, helmets, safety shoes, etc.
If the project completion acceptance meets the requirements, it shall be terminated after paying off the project payment, and the warranty liability shall still be retained.
3.
2.
In the process of construction and operation, Party B’s members who do not meet the requirements of Safety specifications, dismantle the safety enclosure by themselves, violate the operating procedures, operate after drinking, play or fight, regardless of the size of the accident responsibility, shall be borne by Party B.
The construction period shall be postponed accordingly in case of the following circumstances: 1) the employer requires to change the confirmed design scheme, which will affect the project progress; 2) power failure and water supply for more than 8 hours within a week for reasons other than the contractor, affecting normal construction; 3) the next process construction is affected due to the employer’s reasons; 4) the construction period is delayed due to force majeure factors such as bad weather (rainstorm, high temperature, earthquake, typhoon) and government administrative actions; 5) Other circumstances in which the employer’s representative agrees to postpone the construction period.
v.
All responsibilities have nothing to do with Party A, and Party A shall not be responsible.
2.
safety responsibility 1.
7、 Payment and settlement of project funds} 1.
In case of any problem, it shall be on call to ensure the normal use of the contracted project.
This contract is made in duplicate, with each party holding one copy.
general rights and obligations of both parties.
III.
Calculated from the date of signing the contract.
the tools, equipment and performance during construction must be safe and reliable, and can not operate with “disease” or overload.
Responsibilities of the employer: 1) be responsible for coordinating the relationship between various construction units and on-site construction supervision.
2.
If the construction period is delayed due to Party B, Party B shall pay 0.05% of the payment payable as liquidated damages every day.
The contract shall come into force after being signed and confirmed by both parties.
Dispute resolution.
3) timely make technical disclosure to Party B, solve the difficult problems in the construction drawings and operation process, and check and correct the errors and deficiencies of Party B in the operation process.
The remaining 5% shall be used as the project guarantee fund and shall be paid within 3 months after the completion acceptance.
During the performance of the contract, the data, drawings, notices, visa lists, contact lists, meeting minutes, etc.
If either party violates the provisions of the contract, it shall be settled by both parties through negotiation.
2.
confirmed by both parties shall be regarded as annexes to the contract and have the same binding force as the contract..
project overview {1 Project Name: 2 Project address: 3 Project nature: the main concrete brick structure project of the construction project (including auxiliary materials) II.
Party A shall be informed in writing of the required materials one week in advance.
In case of quality problems during construction, the Contractor shall timely report to the employer’s representative and solve them together.
If the negotiation fails, it can be settled through litigation by the arbitration organ or the people’s court where the project is located.
3.
Click the blue word to pay attention to us for emergency needs ~ the employer of the concrete brick structure construction contract: (hereinafter referred to as Party A) the Contractor: (hereinafter referred to as Party B) in accordance with the contract law of the people’s Republic of China, the construction law of the people’s Republic of China and relevant laws and administrative regulations, Following the principles of equality, voluntariness, fairness and good faith, in order to clarify the rights and obligations of both parties, the following contract terms are reached through friendly negotiation: I.
2) make three supplies and one leveling on the construction site to ensure good power supply and water supply.
During the construction, Party B shall unconditionally accept and bear the personal injury, property loss or liability accident and civil liability caused by materials, tools and equipment, installation and construction procedures or negligence of behavior.
Responsibilities of the Contractor: 1) organize professional construction personnel to carry out the project construction, determine the implementation plan and safety scheme, actively transport the equipment and tools used in the construction to the site, and prepare the tools and equipment required for the construction in advance.
6、 Project quality} 1.
4) Save materials and eliminate waste.
After the contract is signed and takes effect, Party A shall pay 95% of the project funds according to the project progress.
2.
The quality of the project meets the requirements of the following standards and specifications: 1) unified standard for construction quality acceptance of construction projects (GB50300-2001); 2) code for acceptance of construction quality of masonry structures (gb50203-2012); 3) Relevant national and Dongguan laws, regulations, specifications and standards have reached the qualified level.
9、 Appendix 1.
The contract price is settled according to the construction area of the construction drawing, with a total construction area of ㎡, RMB per square meter, and the total contract price is RMB (¥).