Acceptance contents of concealed works ➤ pile foundation works (1) pile foundation axis and sample pile setting out, positioning and review records.
(8) Floor works: concealed works shall be accepted for each structural layer; Treatment of deformation joints.
(3) Cushion (including elevation, length, thickness, width and concrete strength grade).
(6) Curtain wall works: embedded parts (or post embedded parts), connecting nodes of components, deformation joints and structural nodes at wall corners, curtain wall lightning protection devices; Fireproof structure of curtain wall.
(2) Whether the conduit is fixed and whether the conduit connection is firm.
The design unit must be present for important foundations such as cast-in-place pile foundation.
➤ axis of foundation engineering (1): the construction unit shall fill in the construction survey inspection application form (inspection application form), and attach the construction survey setting out review form.
(4) Light partition wall works: wood keel fire prevention, anti-corrosion treatment, embedded parts or tie bars, keel installation, and setting of filling materials.
(3) Gutters, eaves gutters, flashing and deformation joints.
After concealed works are concealed, if quality problems occur, they need to be covered and covered again, which will cause great losses such as rework.
(2) Earth excavation (including design elevation, concealed Creek, geology, foundation trench width, length, grading and slope): the construction unit shall fill in the foundation trench inspection record.
(4) After the construction team passes the inspection, the person in charge of construction of the construction team shall sign the concealed works acceptance certificate and report it to the project department for inspection.
(8) Installation of overhead slab (including floor slab model, seam separation of lower floor slab, laying length, hard leveling, soft setting mortar; quantity, specification and length of anchor bars of overhead slab).
This is called a great husband—— Mencius concealed works generally refer to the works that need to be covered and covered, such as foundation, electrical pipeline, water supply and heating pipeline, etc.
(3) Reinforcement of cantilever parts such as awning, balcony and air conditioning board (once per floor), patrol inspection and side station records.
If any, they shall be replaced..
(7) Detail works: connection nodes of embedded parts (or post embedded parts), guardrails and embedded parts.
➤ building decoration works (1) plastering works: strengthening measures when the plastering thickness is greater than or equal to 35mm; Strengthening measures at the junction of different material substrates.
(4) Concrete (including surface quality, strength grade and once for each layer), patrol inspection and site record.
(2) Door and window works: embedded parts and anchors; Anti corrosion and filling treatment of concealed parts.
➤ roof engineering (1) base course of coiled material and coated waterproof layer.
(7) Parapet coping reinforcement (including quantity and specification).
(2) Pile driving (pressing) construction records and pile forming construction records of cast-in-place piles.
(4) Lap width and additional layer of coiled material and coating waterproof layer.
(5) Concrete (including section size, elevation, honeycomb, pitted surface, exposed reinforcement and concrete strength grade): concrete pouring order and concrete grading sheet.
(7) Reinforcement of damp proof course (including quantity, specification, variety and overlapping length).
Inspirational sayings: wealth can’t be prostituted, poverty can’t be moved, and power can’t be subdued.
The construction can be carried out only after the inspection results are qualified.
(5) Wall masonry (including quantity, specification and setting of tie bars between column and wall), mortar grading sheet.
(3) After the construction of concealed procedures is completed, the construction records must be filled in after passing the self inspection by the construction director, and signed by the team leader, quality inspector, technician and inspector, and then signed by the on-site supervisor.
(5) The isolation layer between the rigid protective layer and the coiled material and film waterproof layer.
(2) Column, beam, stair and slab reinforcement (including quantity, specification, variety, overlapping length, welding condition, thickness of protective layer, stirrup spacing, embedded parts, etc., once per layer), patrol inspection and on-site record.
(3) Ceiling works: wood keel fire prevention and anti-corrosion treatment; Embedded parts or tie bars; Boom installation; Keel installation; Fill material settings.
The following is a summary of 61 key points related to concealed works acceptance, in place! Acceptance process of concealed works (1) before the commencement of concealed works, the project department shall be responsible for inspecting the materials used.
(5) The project department shall conduct spot check on the concealed works, check the construction records, sign on the concealed works acceptance certificate after confirmation, and report to the engineering supervision department of the supervision company for inspection.
(6) Reinforcement of roof water tank (including quantity, specification, variety and lap length), patrol inspection and on-site record.
(6) The supervision company shall conduct spot check on the concealed works, check the construction records and material quality certificates, and sign on the concealed works acceptance certificate after confirmation.
(2) The construction of concealed procedures shall be carried out under the supervision of supervisors, chief engineer of the project and full-time quality inspectors.
The inspection contents include: material certificate provided by the manufacturer, appearance inspection, sampling test and re inspection report conducted by the project department.
(3) Precast pile connection, bored pile drilling and hole cleaning, reinforcement cage fabrication, hoisting and concrete pouring.
(2) Seal the waterproof treatment part.
(6) Foundation wall (including elevation, large foot size and masonry mortar strength): mortar grading sheet.
➤ whether various materials used in Circuit Engineering (1) meet the design requirements and whether the spacing between strong and weak tubes is more than 500mm.
The construction of concealed procedures shall be carried out in strict accordance with regulations, specifications and operation instructions.
(4) Acceptance record of pile position axis deviation and elevation (if the elevation of pile top is the same as that of the construction site, it shall be carried out after the construction of pile foundation works).
(3) All lines in the threading pipe shall be free of joints and kinks.
Therefore, concealed works are often accepted in order to ensure the quality of the project and the smooth completion of the project.
(4) Bottom plate reinforcement (including variety, specification, quantity, overlapping length, stirrup spacing, thickness of protective layer, quantity and position of embedded parts).
(5) Decorative panel (brick) works: embedded parts (post embedded parts), connecting nodes and waterproof layer.
➤ axis and setting out of main works (1) (each floor).