Construction organization of battery production project – 92 – level III Inspection and process handover

② Process handover inspection refers to the inspection of the previous process by the operator of the next process.

Solar power stations, solar water heaters, electric vehicles and energy storage power stations are all based on the mass production of batteries, and solar cell production is the demand side of purification projects.

More contents: 1 – project overview 2 – wastewater treatment station 3 – bulk gas station 4 – construction objectives 5 – high altitude operation 6 – overall arrangement of project implementation 7 – arrangement of construction team 8 – main construction stage 9 – construction method of divisional and subdivisional works 10 – elevation measurement control 11 – settlement observation 12 – installation of embedded anchor bolts 13 – Determination of bolt position 14 – formwork removal Concrete curing 15 – Super leveling professional construction 16 – floor construction process 17 – cover and protect with film 18 – formwork installation 19 – concrete pouring 20 – concrete surface treatment 21 – steel structure fabrication 22 – detail design 23 – connection node design 24 – steel structure fabrication process 25 – steel structure processing and fabrication process 26 – setting out Allowable deviation of template 27 allowable deviation of steel after correction 28 cutting 29 allowable deviation of sawing 30 allowable deviation of refined bolt hole 32 allowable deviation of bolt hole spacing 33 assembly principle 34 principle of steel plate splicing 35 allowable deviation of welding structure assembly 36 H-section steel assembly 37 welding H-section steel column fabrication 38 welding process flow chart of steel structure 40 welding rod Table 41 – General Provisions for welding flux selection 42 – submerged arc welding 43 – CO2 gas shielded welding 44 – carbon arc gouging 45 – welding sequence 46 – member derusting method and inspection standard 47 – steel member coating method 48 – derusting and repair of coating defects 49 – Parts prohibited from painting 50 – protection and transportation of finished products 51 – steel structure installation 52 – hoisting of steel columns 53 – roof truss installation and construction 54 – high strength bolt installation 55 – profiled roof panel installation 5 6 – positioning of fixed support 57 – Installation precautions 58 – Installation of sandwich color plate wallboard 59 – fire retardant coating of steel structure 60 – binding of beam and plate reinforcement 61 – binding of column reinforcement 62 – column formwork 63 – beam and plate formwork 64 – stair formwork 65 – precautions for construction of wood plywood formwork 66 – concrete engineering 67 – beam Slab concrete 68 – concrete curing 69 – masonry construction 70 – roof waterproof construction 71 – plastering construction 72 – emulsion paint wall construction 73 – ceiling construction 74 – penetration crystallization wear-resistant floor construction 75 – floor tile floor construction 76 – epoxy floor construction 77 – rolling shutter door installation 78 – aluminum alloy window installation 79 – water supply pipe installation 80 – drainage pipe installation 81 – electrical piping and threading in pipe 82 – lightning protection and grounding works 83 – construction schedule 84 – construction progress control flow chart 85 – resource assurance measures 86 – technical measures 87 – management measures 88 – quality management organization structure 89 – quality management responsibilities 90 – quality education system 91 – concealed works acceptance and technical review 92 – three-level inspection and process handover, more purification communication groups, recognition and implementation of group regulations, Welcome to “purify the four groups and follow the rules” (open the link to see details.) For more purification materials, please refer to “borrow 69 purification materials for free 20211130”, “share 2 yuan for 36 purification materials”, “video, audio and articles, the purification you want is here”, whether it is “like the author” or forwarding, or even open the advertisements automatically added in and behind the text, Can add a “Shandong big steamed bread” to Xiaobian********************** Chat up Xiaobian..

If the previous process is not accepted, the next process shall not be inserted.

In case of special circumstances, they can be accepted by parts and the inspection application form can be filled in uniformly.

Cast In Loop

team self inspection, constructor re inspection and special inspection by full-time quality officer.

Thank # warm Meng for pursuing excellence and Zhai Lijuan for sharing the materials.

④ Inspection application procedure ⑤ the acceptance parts shall be applied for inspection according to the floor or independent area in principle.

Therefore, starting today, I will share the construction organization design of solar cell production projects with you.

6.4.4 three level inspection and process handover inspection ① three level inspection system, i.e.

③ The unqualified processes and parts shall be reworked resolutely, the quality problems shall be analyzed, and pre control and preventive measures shall be formulated to prevent the same quality problems.