The preparation plan, approval, review and change process are as follows: the approval management process of the general contractor’s construction organization design and construction scheme needs to change the general construction organization design and construction scheme, In addition to the supervisor’s approval, the construction scheme of important parts in the change process shall also be submitted to the design unit for approval, and shall be copied to the owner and the project management company for filing after being reviewed by experts or administrative approval units.
According to the overall construction schedule and construction deployment of the general contractor, each electromechanical subcontractor shall organize technical forces to carry out special construction organization design and professional construction scheme preparation.
A large-scale engineering project, the Luban Award project, may need to prepare nearly 100 construction organization designs and special construction schemes.
2、 Mechanical and electrical construction scheme management professional construction organization design and professional construction scheme are important technical documents for the implementation of professional projects.
After the preparation, the general contractor’s technical management process needs to be approved and reviewed accordingly.
management approval process of professional subcontracting construction scheme IV.
All special schemes and professional construction organization design shall be prepared by each party according to the preparation responsibility.
The preparation requirements and approval management process of the sub divisional construction organization design and construction scheme of each electromechanical discipline in the project are as follows: approval process III.
management approval process of independent subcontracting construction scheme source: more legal consultation in Chengdu, Sichuan in the engineering management circle, Please call lawyer Yang Hua at 13980986153 [copyright notice]: the picture and text of this article.
The final review document will be used as the basis for the owner, the project management company, the supervisor and the general contractor to inspect the construction process of each electromechanical discipline subcontracting.
The management of professional construction organization design and professional construction scheme is a very important work content for the general contractor’s technical management and coordination of professional projects.
1、 The construction organization scheme to be prepared by the general contractor is the construction organization design and main special scheme prepared and organized by the general contractor.
The review and approval of construction organization design and special scheme are of great significance to the standardized management of the project.