Answer: the picture of the construction site asked: why is the road still pitted when the enclosure is removed? In order to restore vehicle traffic as soon as possible, the construction enclosure has been removed in advance on January 21.
11 heavy news!!! The construction enclosure of Donghe bridge head of Chengcheng road has been completely removed! Vehicles can be opened to traffic normally!!! On October 17, 2021, the construction of enclosure at the Donghe bridge head of Chengcheng road began, and the construction enclosure hindered our passage Block! Block! Block! It’s almost Chinese New Year.
Organize and implement the sewage pipe network upgrading project (phase I) of dongheyi Road, Baise City.
When will it be open to traffic? Recently, many citizens have raised a lot of questions Come on, come on! The exact news came out! On January 21, the construction enclosure of Donghe bridge head of Chengcheng road has been completely removed and the road has been restored to smooth traffic! The picture of the construction site asked: what are you doing after three months of enclosure? It turned out that Baise urban management and Supervision Bureau changed the current situation of rainwater and sewage confluence in dongheyi road in order to improve the sewage collection rate of our city.
A: responsible leader: Lu Wenyong reviewed by: Huang Xiaoqing source: Yesong urban operation center, making citizens comfortable.
A: when will the enclosure at the side door of the city hospital be removed? At present, the construction is in full swing.
The design starting point of the project is the intersection of dongheyi road and Chengcheng Road, and the end point is the intersection of dongheyi road and Jiangbin second road.
After the rain stops and the pavement is dry, the excavated pavement will be paved with asphalt and restored according to the original pavement structure layer.
It is expected that all fences can be removed and the recovery of pavement structure layer can be completed on the 26th.
Due to the influence of rainfall, asphalt cannot be paved according to the original construction plan.