What are the hazards of white map construction? What is the difference between a white picture and a blueprint?

Article 58 of the construction law of the people’s Republic of China stipulates that construction enterprises are responsible for the construction quality of the project.

If the construction unit finds errors in the design documents and drawings during the construction process, it shall put forward opinions and suggestions in time– The situation of white map construction continues despite repeated prohibitions.

In addition, the construction unit shall also compensate for other losses caused by white drawing construction.

Construction according to drawings cannot be simply understood as construction according to the drawings provided by the construction unit.

The regulations on the quality management of construction projects stipulates that the construction unit shall not express or imply that the design unit or construction unit violates the mandatory standards for project construction and reduces the project quality.

In practice, if white map construction really occurs, what adverse consequences will it cause to the construction unit– First, the construction unit may be subject to administrative punishment.

Construction drawings that have not passed the examination shall not be used– It is said that white drawings cannot be used as the basis for construction.

In case of any adjustment to the planning during the construction using the blueprint, the construction unit shall be required to improve the planning procedures and provide the compliant construction blueprint.

In practice, white drawing construction is not allowed for any reason! “Construction according to drawings ≠ construction according to the drawings provided by the construction unit”, the construction unit should pay great attention to the use of construction drawings.

Construction according to blueprints should be taken as the bottom line during construction, and unapproved white drawings should be rejected.

Please let us know if there is infringement! If you like, click to read other hot literature materials: explain the pipeline knowledge at once, strong! The whole process of water and electricity installation is complete! 17 process points of bridge and cable construction, examples of high-quality projects, a full set of air conditioning design reference notes, how to accept the mobilization of common materials in electromechanical installation engineering? Standard summary! Is the return water of floor heating water supply not hot? Generally these six questions! Super analysis of quality problems and construction practices in each stage of multi line installation project 15 pictures + 1 Video: quickly understand the principle, structure, classification and complete process of water and electricity installation of screw compressor..

The regulations on the quality management of construction projects stipulates that the review organization of construction drawing design documents shall review the contents of construction drawing design documents of housing construction projects and municipal infrastructure projects involving public interests, public safety and mandatory standards for engineering construction.

The transportation and other relevant departments of the people’s governments at or above the county level shall, in accordance with their duties, examine the contents of the construction drawing design documents involving public interests, public safety and mandatory standards for engineering construction.

Moreover, the administrative penalty will be recorded in the credit information of the enterprise, which may affect the work of the enterprise in government procurement, project bidding, transfer of state-owned land, awarding honorary titles and so on.

The original design unit shall be responsible for the modification of the engineering design, and the construction enterprise shall not modify the engineering design without authorization.

If the construction drawing design documents provided by the construction unit are not examined or fail to pass the examination, the competent government department will order it to make corrections and impose a fine of not less than 200000 yuan but not more than 500000 yuan.

In a word, white drawing construction has a lot of risks for the construction unit.

Sharing is a virtue.

The construction unit uses white drawings for construction.

In case of any of the above matters, the construction unit shall be notified in time and recorded in the construction log and minutes of regular supervision meeting, The supervision unit is required to make detailed records in the weekly supervision report to provide evidence support for the construction period claim.

China implements the review system of construction drawing design documents (including survey documents).

The construction unit shall not carry out construction in violation of the drawings and construction technical standards.

Secondly, the construction unit should bear the quality responsibility.

Spread Anchor

Construction drawings that have not passed the examination shall not be used.

The construction unit must carry out construction in accordance with the engineering design drawings and construction technical standards, and shall not modify the engineering design without authorization or cut corners on work and materials.

If the construction unit fails to construct in accordance with the approved drawings, regardless of whether the construction quality is qualified or not, it will be fined not less than 2% but not more than 4% of the project contract price.

If the construction unit fails to use the compliant drawings for construction, resulting in the quality of the construction project not meeting the specified quality standards, it shall be responsible for rework and repair, and compensate for the losses caused thereby; If the circumstances are serious, it shall be ordered to suspend business for rectification, reduce its qualification level or revoke its qualification certificate.

The construction and supervision of housing construction projects and municipal infrastructure projects, as well as the quality and safety supervision and management of housing construction and municipal infrastructure projects, shall be based on the qualified construction drawings– What should the construction unit and the construction unit do respectively to avoid white map construction– The construction unit shall not provide drawings that are not approved and qualified.

Even if the construction is carried out in accordance with the construction drawings provided by the construction unit, in case of project quality problems, the construction unit shall still bear some responsibilities, including the repair of project quality and compensation for the rental loss of the construction unit (if any), which will lead to the risk that the project funds cannot be recovered in full.

At the same time, it shall explicitly refuse to construct according to the white drawing, and the construction can be continued only after the construction unit provides the compliant change drawing.

Is there any basis– Construction drawings shall not be used without passing the examination, which is expressly stipulated by laws and regulations.

As the basic and programmatic documents of project construction, the construction unit, design unit and construction unit shall follow their legal compliance principles and review the contents of construction drawings involving public interests, public safety and mandatory standards of project construction in accordance with relevant laws and regulations, After completing the necessary construction drawing review procedures, the compliance drawings can be provided for the construction unit to carry out the project construction.

Construction enterprises must carry out construction in accordance with engineering design drawings and construction technical standards, and shall not cut corners on work and materials.

Here will build your “hive of thought” # what is the construction of white map? The so-called compliant drawings should be the drawings stamped with the seal, the signature of the registered architect and the structural engineer, that is, the construction blueprint, otherwise it is the construction white drawing.