▲ fully enclosed detour plan of Dawang Avenue rapid three-dimensional traffic upgrading project (Zhengde Street).
Traffic relief personnel are set at the intersection of Zhengde street and TIYU East Road to command, release the relevant vehicles of the power supply bureau, and other social vehicles bypass.
The project is the upgrading and widening of the existing road, and the existing driving road shall be occupied during construction.
West of Zhengde Street: the vehicles in and out of the power supply bureau are still driving on the same road.
Double Head Lifting Pin Anchor
Source: issued by Zhaoqing hi tech..
Vehicles passing through this section of Zhengde Street bypass Shuguang street and Industrial Street; Road closure warning signs shall be set at the end of horizontal sealing.
Traffic relief personnel are set at the intersection of Zhengde street and Beijiang avenue to command, release relevant vehicles in the above three places, and other social vehicles bypass.
Road closure announcement: comprehensive development and upgrading project of Qilin Lake area of Zhaoqing high tech Zone – rapid three-dimensional traffic upgrading and reconstruction project of Dawang Avenue, in which the intersection of Dawang Avenue and Zhengde Avenue in bid section 3 is fully closed.
Closing time: January 10, 2022 – February 20, 2022.
▲ fully enclosed plan of Dawang Avenue rapid three-dimensional traffic upgrading project (Zhengde Street).
The two-way carriageway of Zhengde street is fully enclosed for construction.
East of Zhengde Street: vehicles entering and leaving runlihuating, Dong’ao imperial garden and China railway project department are still running on the same road.