On January 20, the pile test project of six bid sections of Yancheng section of Binhuai expressway was started at the same time, marking that the project has entered the full construction stage.
It is connected to Chang Shen expressway.
On the north side of Haibin town and the planned north side of Haibin Town, it continues to cross Haibin town on the north side of Haibin economic Park on the 204 side of Haibin expressway, which starts from the north side of Haibin town on the north side of Haibin town, After crossing the modern agricultural industrial park with the planned S27 Linyan expressway, it is connected to the Lianshui section of Binhuai expressway.
It has a total length of about 65 kilometers, two-way four lanes and a design speed of 120 kilometers per hour.
After 15 minutes, a pile with a depth of more than 7m was driven.
After the completion of Binhuai expressway, it will greatly improve the travel speed of the surrounding people, and also play an important role in improving the collection and distribution capacity of Yancheng coastal ports, promoting the integrated development of industries and cities along the line, and supporting the in-depth implementation of Huaihe River ecological economic belt.
It was officially started on November 19 last year.
It is planned to be completed and opened to traffic in November 2024.
From east to west, it passes through six towns (districts and streets) including Binhai Port Economic Zone, Binhuai farm, Binhuai Town, Baju Town, Jiepai Town, kanbei street and Tianchang town.
The Binhai section of Binhuai expressway is provided with 2 hubs (G15 Binhai hub and S27 sets of hubs), 5 Interchanges (g228 Binhai port interchange, S226 Binhuai interchange, planned S226 boundary card interchange, G204 Binhai West interchange and s327 sets of Interchange), and 1 service area (Binhai North Service Area).
At 9 a.m., at the project site of bid section 2, with the roar of the machine, the spiral blade of the cement mixing pile machine quickly broke through the surface and went deep into the ground.
The project line starts from Binhai port area in the East and ends in Lianshui County, Huai’an City in the West.
The total length of the line is 16.75 km, which is an important part of Yancheng section of Binhuai expressway.
New progress has been made in Yancheng section of Binhuai expressway.
Bid section 2 of Binhuai Expressway contracted by China Railway Shanghai Engineering Bureau starts from the end of Binhuai interchange and ends before boundary card interchange.
It is reported that Yancheng section of Binhuai expressway is an important part of the “horizontal and four lines” (S18) in the “15 shooting, 6 vertical and 10 horizontal” of the Jiangsu Expressway Network Planning (2017-2035) approved by the provincial government.
Look forward to it together! Source: Yanfu Dazhong newspaper group and Yancheng release comprehensive arrangement reporter: Cai Bingqing intern reporter Hu Bei group draft: Zhao Xinli editor: Han Xinxu Cai Yue praise first, then “watching” and walk hand in hand with Yancheng ↓↓↓..
There are 2 hubs, 5 interchanges and 1 service area along the whole line.