Should the construction party break the contract and stop the loss when the material price rises sharply? The real case is judged like this!

After that, the two sides signed a construction contract for the project involved.

Employer: Xin * company contractor: Chen * company first instance court: Huai’an qingjiangpu District People’s Court (2017) Su 0812 minchu No.

Reject other litigation claims of the employer.

Judgment of the court of first instance: rescind the construction contract of steel grating project of production workshop of Jiangsu Xin * tobacco flake Co., Ltd.

On March 24, 2017, the law firm sent another letter to the contractor, saying that the Contractor’s forced unilateral termination of the contract has constituted a serious breach of contract, and the employer is unable to return the performance bond, and reserves the right to investigate the losses of the employer caused by the breach of contract.

On September 22, 2016, the employer and the contractor signed a construction contract for the construction project, with the contract price of 1414378.71 yuan.

The contractor paid 142000 yuan of performance security to the employer.) On March 19, 2017, the contractor sent a letter to the employer, saying that the market price of steel had increased more than twice as much as when the contract was signed, requiring the employer to adjust the contract price to 2957394.99 yuan, and then the contractor began to perform the contract.

8 2016, The employer will invite public bidding for the “steel grating project of production workshop of the supporting engineering construction project of reconstituted stem verification production line”.

The employer refuses to accept the judgment of first instance and appeals to the intermediate people’s Court of Huai’an City, Jiangsu Province.

The court of first instance held that if a party fails to perform its contractual obligations or fails to perform its contractual obligations in accordance with the agreement, it shall bear the liability for breach of contract such as continuing to perform, taking remedial measures or compensating for losses.

Due to the Contractor’s failure to perform the above contract, the employer again invited tenders for the project involved.

The pricing method of the project agreed in the contract is fixed unit price, and the rise of material price is the risk under the contract.

According to the guide price of Huai’an construction engineering materials recorded in the magazine Huai’an engineering cost management published by Huai’an engineering cost management office, the overall price level of Huai’an steel was rising from August 2016 to April 2017, but the average monthly increase was relatively stable, which was a gradual rising process.

Straight Anchor

On March 27, 2017, the contractor sent a letter to the employer requesting to terminate the construction contract and return part of the performance bond as appropriate.

The employer believes that there is no basis for terminating the contract on the grounds of rising material prices and requires continued construction.

After the signing of the contract involved in this case, the steel price rose, but the rise is a gradual evolution process, not a sudden change process that caught the market subject off guard.

On March 22, 2017, the employer entrusted a law firm to send a letter to the contractor, saying that both parties must perform their contractual obligations according to the contract.

The court of second instance held that the Contractor’s failure to perform its construction obligations as agreed in the contract constitutes a breach of contract and should bear the corresponding liability for breach of contract..

On May 25, 2017, Zhuozhou blue * Grid Co., Ltd.

The contractor unilaterally terminates the contract.

Therefore, the Contractor’s argument on the change of situation is not accepted.

In the first instance judgment, the employer appealed to the people’s Court of qingjiangpu District, Huai’an City on August 31, 2017.

If the Contractor fails to perform its obligations in accordance with the contract and is at fault, it shall bear the corresponding liability for breach of contract.

reconstituted stem verification production line construction project signed by the employer and the contractor on September 22, 2016; The Contractor shall compensate the employer for the default loss of 142000 yuan (offset by the performance bond).

From China judicial document network, case study of engineering cases and construction management.

Claim: rescind the construction contract of steel grating construction project of production workshop signed by both parties; The Contractor shall compensate the employer for the loss of 1850038.63 yuan (the price difference between the two tenders is 1691319.63 yuan, the construction delay is 70719 yuan, and the lawyer’s fee is 88000 yuan).

In the face of soaring material prices, should the construction party stick to the contract to continue construction or suggest default stop loss? Conversely, if the price of materials plummets, should the employer stick to the contract or break the contract and make profits? The following real case may bring some thoughts.

On August 29, 2016, the contractor bid and won the bid, and the bid winning price was 1414378.71 yuan.

There is no basis for terminating the contract on the grounds of the rise of material price, and asked the contractor to ensure the construction on April 1, 2017.

Other losses claimed by the employer shall not be supported due to insufficient evidence.

(article 3.7 of the contract stipulates that the Contractor shall provide performance security in the form, amount and period of 10% of the total contract price.

The employer brings a lawsuit.

Considering that the project involved is the steel grating project of the production workshop, and the main material required for the project is steel, the objective fact that the steel price has increased nearly twice by the commencement date agreed by both parties in the contract, and there is no evidence that the contractor deliberately fails to perform its obligations under the contract, combined with the provisions of the performance bond in the contract between both parties, The court of first instance decided that the contractor should compensate the employer for the default loss of 142000 yuan (offset by the performance security paid by the Contractor).

103 retrial Court: Jiangsu High Court (2020) Su minzai No.

Brief introduction of the case: due to the sharp rise in the price of main material steel, the contractor proposed to terminate the construction contract and refund part of the performance bond as appropriate.

7343 civil judgment second instance court: Huai’an Intermediate Court (2018) Su 08 Minzhong No.

On March 21, 2017, the contractor sent a letter to the employer, saying that it was unable to perform the contract due to major changes in the market price of steel, and notified the employer to terminate the contract and return the deposit.

Otherwise, the contract was terminated and the employer was required to return the deposit of 142000 yuan and was willing to accept a fine of 10000 yuan.

won the bid with a bid price of 3105698.34 yuan.