Visa items most likely to be missed on the construction site

If Party A does not agree on the progress or the agreement is not detailed enough, Party A can try to postpone the work to strive for claims in its own favor.

The calculation in this is quite complex.

[cooperation fee] I didn’t expect that the cooperation fee can also be visa, right? The cooperation fee is only that you provide water supply, electricity, scaffold, vertical transportation and other cooperation for other subcontractors to complete their processes (note that the water and electricity fee is also not included in the cooperation fee, depending on how the contract is agreed).

The pump shift is not cheap, so the pump model should be written with [vertical transportation], which is similar to the formwork part.

If the negotiation fails, it will ask Party A for a visa and withhold its project funds.

[template part] now many projects are priced by list.

If it does not exceed the scope of the list, it is OK.

If there is a construction period requirement during the construction, check it first.

It is no problem to demolish the wall, but the visa must explain the damage degree of the brick (otherwise the audit will directly reduce the materials for you).

[finished product protection] finished product protection is not innate.

If a large amount of drainage or quicksand treatment, it can be signed.

The only thing to pay attention to is that overtime also increases a series of efficiency reduction expenses such as mechanical operation salary.

The price of wet soil is higher than that of dry soil, and the price of sludge excavation is higher.

Everyone knows that the oil price is so expensive now.

Click the blue font above to subscribe for free! [earthwork part] groundwater is not considered in earthwork bidding.

If sufficient backfill soil cannot be stacked on site due to narrow site or unstable slope, the outward earthwork volume and haul distance shall be signed.

If it is enough for visa, it’s good to form a habit.

Some things are unreasonable..

In the foundation construction, the brick formwork is used in response to the requirements of Party A to speed up the progress or considering the instability of the slope and the need to backfill as soon as possible.

If the conditions are not enough, don’t fool around with a small sump and be careful to go through the gang.

It’s not that you have finished product protection of marble when you shop marble, but that you have done finished product protection seriously.

If Party B also participates in the work, it can negotiate with Party A.

The cost of clearing underground obstacles is not cheap.

Some list measures are not clearly listed, causing trouble in subsequent settlement.

If there are underground obstacles, it should be verified.

Pay attention to the well point.

This is a fair and aboveboard rush work fee, but in fact, everyone didn’t want it.

If it is not specified, it is likely to be cut directly for you.

if you master the know-how, you can cut in at a low price during bidding.

Of course, if the construction is suspended for a long time, the suspension period must be recorded, and it must be remembered that the visa should not be delayed until the construction is started.

Even if you take a penny to surround the scene and spread a broken sack, you should prove it as soon as possible.

The earthwork transportation distance naturally depends on whether it is beneficial.

If there is water seepage in excavation, the height of groundwater level can be verified.

If the damage is not serious, the loss rate and secondary use of the brick can be signed to remove ash scars, slag, etc.

[roof] the roof is often changed by Party A.

There is also the template added for rush work.

According to the legal construction period or the bidding construction period, the speed required by Party A now leads to the increase of the number of sets of templates.

It is recommended to refer to relevant publications for more understanding.

At the same time, it also reminds us: 1.

Therefore, the visa added in the template is particularly important.

Halfen Frimeda

If you can’t get the well point, you should strive for pump dewatering.

These can’t be verified afterwards.

If the excavated soil is transported away and backfilled, it will not be counted as money if the cost is not signed.

If there is a requirement to mention it in the contract, the additional requirement will be paid.

You should give as much as you sign.

The template is solved by one item.

In addition, if the water seepage is large, the construction scheme can also be prepared to apply for drainage and dewatering measures and slope support measures.

2.

Otherwise, the supervisor of Party A cannot be assessed for a long time, and it will be very troublesome to sign in the later stage.

When these leaders who like to change invented a new roof method, it will look good to recalculate the unit price.

Because most of the bids consider the on-site stacking of soil, and the remaining soil is transported out.

If it encounters rock, it should sign the depth into the rock in time.

Although it can be argued, it is always good to do things ahead.

However, if the subcontractor damages or pollutes your things, it will not ask him for it.

When calculating the unit price, don’t forget the exhaust pipe and pipe fittings of the insulation layer, the oil impregnated wood wool board and ointment caulking of the surface protective layer.

If it exceeds the scope, the transportation distance must be signed.

3.

The concealed records shall also be as detailed as possible, that is, at least: hole depth, pile length, reinforcement cage length, empty section length, pile diameter and rock entry depth.

During the foundation construction period, if the construction period is suspended due to rain or delayed due to Party A, the drainage and precipitation expenses can be signed according to the unit shift.

During the construction, Party A has no right to add terms, saying that the top cannot be closed for a few months and days, and how much penalty will be imposed for a day’s delay.

[precipitation and drainage] the drainage in the quota is only the drainage of surface water and a small amount of open water.

It should be done at least once a month, which is also the principle of long-term visa.

[masonry part] the most common occurrence of masonry is that it is demolished and demolished.

The construction unit shall be responsible for the three supplies and one leveling of the site.

Although you don’t have much money, it’s not cost-effective to be cut down.

If there is no requirement at the time of bidding, it can also be signed, and the price of brick formwork is higher than that of formwork erection.

[pile foundation part] in addition to making records of concealed works, the pile foundation should also pay attention to the visa of underground obstacles.

If the foundation construction is suspended or delayed, it should be signed.