Broadcast of construction progress of zhongruizhizao science and Technology Industrial Park in May

Trapezoid Rubber Magnetic Chamfer

In May, the construction progress was broadcast that the erection of the woodworking frame on the second floor of the seventh # building was completed, the pouring of the foundation ground beam on the eighth # building was completed, the pouring of the foundation ground beam on the ninth # building was completed, the foundation earthwork excavation on the tenth # building was completed, the foundation earthwork excavation on the 13th # building was completed, the main structure of the 15th # building was capped, the woodworking work in the basement of the 16th # building was completed, 70% of the main structure on the third floor of the 17th # building was completed, and the main structure of the third floor of the 18th # building was capped; During the construction of secondary structure, 19# building foundation cushion shall slide left and right to see the effect drawing..