Teach you how to write the supplementary agreement of the general contract for construction engineering 18

2.

Article 6 Determination of the contract price 1.

Project payment method: for the main works of the basement, after Party B completes the main works of the basement, Party A shall pay 60% of the main works of the basement, 80% of the completion of the five floors of the main works above the ground, 80% of the completion after capping, 90% of the monthly progress of the secondary structure works, 97% after the completion of the project, 5% of the quality deposit left by Party A and settled within two years.

Settlement method of labor and material cost: 1) except for the materials provided by Party A in this contract, the rest shall be purchased by the contractor.

during the construction process, the Contractor shall provide necessary construction cooperation to all professional units: tower crane transportation, construction elevator vertical transportation machinery, scaffold utilization, etc.

2.

3.

Project engineering directly designated by Party A: (elevator engineering; fire control,) Article 4.

4.

Lifting Eye Anchor

From the date of completion confirmation, Party A shall prepare and complete the project completion settlement statement and attachments within half a month, confirm after receiving the project completion settlement statement submitted by the contractor, and complete the review of the project completion settlement statement within three months.

The Contractor shall actively cooperate, If the Contractor fails to submit the project completion settlement statement in time for more than one month, it shall be deemed that the employer defaults that the project settlement price reported by the contractor is true, and shall bear the losses caused to the contractor.

The Contractor shall bear all contractor management responsibilities for the project funds designated by Party A.

Party B shall pay in advance.

2) The cost of water and electricity for the subcontracted project shall be calculated by the external meter of water and electricity on the ground or floor provided by the subcontractor, and shall be paid by the subcontractor according to the actual amount incurred (this cost is a separate cost).

Article 7 review and payment of project funds 1.

Project overview project name: Project Location: building area: the building area is tentatively determined as m2.

confirmed by both parties.

Completion date: mm / DD / 2019.

Article 8 project completion settlement method 1.

Click the blue word to follow us, In case of emergency ~ supplementary agreement of general construction contract of construction engineering employer: Contractor: date of signing: employer: (hereinafter referred to as Party A) contractor: (hereinafter referred to as Party B) according to The contract law of the people’s Republic of China, the construction law of the people’s Republic of China, the regulations on contracting contracts for construction and installation projects, as well as relevant laws and regulations, follow the principles of equality, voluntariness, fairness and good faith, in order to clarify the rights, obligations and economic responsibilities of both parties and ensure the smooth implementation of the project, combined with the specific conditions of the project, through friendly negotiation between both parties and on the basis of full understanding of the terms of this agreement, This supplementary agreement for construction contract of Construction Engineering (hereinafter referred to as the agreement) is hereby signed for mutual compliance.

Project contracting method: contracting labor and materials.

the lines and pipes from the water source and power source to the construction site shall be borne by Party A.

Party A shall pay at the time of settlement.

if the accumulated suspension for non contractor reasons exceeds 15 days, the construction period shall be postponed accordingly.

Article 3 Project contracting scope and content the general contracting scope and content of the contractor are as follows: the contracting scope is: except for the project construction unit directly designated by Party A, all the contents on the construction drawings and the construction tasks designated by Party A.

In case of any of the following circumstances, the contract period can be extended accordingly with the visa and consent of Party A; 1) .

the Contractor shall install meters separately for measurement.

2) .

2) .

Project quality standard: high-quality contract duration and requirements 1.

The cost of material inspection and test shall be included in the project payment after the cost per square meter of construction area is determined.

it shall be implemented according to the fixed labor cost + relevant adjustment documents..

Party A and Party B shall confirm the meter number.

3.

Contract duration: days (calendar days) 2.

Review of project funds: before reaching the payment node, the Contractor shall submit the appropriation calculation sheet, which shall be used as the basis for progress payment after being reviewed by the supervisor and Party A.

2.

3.

Construction water and electricity: the Contractor shall connect to the construction site from the water source and power source designated by Party A.

Commencement date: mm / DD / yyyy (specific subject to the commencement notice issued in writing after the employer obtains the commencement report and meets the construction conditions).

the construction period is delayed due to the irresistible factors of manpower.

During the construction period, the total water meter and electricity meter on the site shall be measured every month, and the person in charge designated by Party A and Party B shall sign and confirm according to the specified sub meter measurement, and the Contractor shall pay for it by itself.

The contract price is tentatively determined as RMB yuan / square meter, in words: RMB yuan only.

Designer: Article 2.

if the Contractor fails to submit the progress calculation sheet according to the actual situation, Party A has the right to postpone the payment of progress payment, and the final settlement shall prevail.

The determination of the project price the contract price shall be based on the construction drawings, constitute various expenses of the project entity and non project entity expenses, and its work quantity calculation, quota application and charging; The civil works shall be subject to the pricing quota of construction projects in Inner Mongolia in 2009; The fee shall be charged according to the standard of fixed rate for pricing of construction projects in Inner Mongolia in 2009, and the fee shall be charged according to class II projects.

3) If Party B needs to issue a project invoice for the construction project directly designated by Party A, materials provided by Party A and the project cost, the specific construction unit shall negotiate with Party B to pay the amount.

General contracting management fee and on-site cooperation fee 1).

The Contractor shall settle the calculation according to the water meter and electricity meter, and the price shall be calculated according to the actual price of the local water supply company and power supply bureau.

The temporary pricing shall not be used as the basis for appropriation and settlement, and the final settlement shall be based on the budget, changes, visas, etc.