Analysis of selected topics in the second construction examination construction management (9)

The tenderer shall fill in the price according to the bill of quantities provided by the tenderee, and the filled () must be consistent with the bidding bill of quantities.

I hope to help you on the road of “textual research”.

Therefore, abce is selected for this question.

[multiple choice] A.

3.

material cost B.

The editor will arrange five exercise questions in Chapter II construction cost management for you, with answers for your reference.

inventory loss of inventory materials D.

[single choice] A.

[single choice] A.

Among the following construction cost analysis methods, the one used to analyze the impact of various factors on the cost is ().

transportation and miscellaneous expenses of materials E.

2.

Therefore, abd is selected for this question.

specific gravity analysis method D.

construction and installation engineering material cost B.

44 document), the following items that should be included in the construction and installation cost are ().

The above is the “dry goods” meticulously prepared for you by Wei Lang education.

Get more information: scan and pay attention to the QR code below, leave a message by private letter, and you can get the relevant reference materials of the constructor for free…

For more information, please continue to pay attention to Wei Lang education.

According to the composition of construction and installation cost items (JB [2013] No.

construction enterprise management cost C.

measure project cost C.

project code D.

enterprise management fee correct answer: B answer analysis: temporary facility cost: refers to the cost of temporary buildings, structures and other temporary facilities for living and production that must be set up by the construction enterprise for the construction of the construction project.

Therefore, C is selected for this question.

project name B.

Lifting Pin Anchor

[single choice] A.

construction and installation engineering measure project cost D.

regulatory fee D.

According to the composition of construction and installation cost items, the cost of protective nets set up by construction enterprises to ensure safe construction shall be included in the construction and installation works ().

Including the erection, maintenance, demolition, cleaning or amortization costs of temporary facilities.

correct answer to project characteristics: A, B, C, e answer analysis: the bidder shall fill in the price according to the bill of quantities provided by the tenderee, and the filled in project code, project name, project characteristics, measurement unit and quantities must be consistent with the bidding bill of quantities.

serial replacement method C.

5.

The expenses for setting up the site office of the construction project management department shall be paid from ().

transportation loss cost C.

correlation ratio method B.

new material test cost correct answer: A, B, D answer analysis: material cost includes the following: (1) original material price; (2) Freight and miscellaneous expenses; (3) Transportation loss cost; (4) Purchase and storage fees.

dynamic ratio method correct answer: B answer analysis: factor analysis method, also known as serial replacement method, can be used to analyze the impact of various factors on costs.

pricing form E.

[multiple choice] A.

In 2022, the construction management examination for grade II constructor is divided into single choice questions and multiple choice questions.

before and during the construction of the project to complete the construction of the project.

measurement unit C.

The site office construction cost in the question belongs to the temporary facilities cost in the measure project cost.

The cost of temporary facilities belongs to the cost of safe and civilized construction, and the cost of safe and civilized construction belongs to the cost of measures.

1.

4.

original material price B.

construction unit management cost correct answer: C answer analysis: measure project cost refers to the cost of technology, life, safety, environmental protection, etc.