Except for reserved construction platform, all raft pouring of West Passenger Station resettlement area 2 and plot 3 project has been

The main buildings of the West Railway Station resettlement area 2 project are five high-rise apartments, supporting facilities, businesses and underground garages.

The area of raft poured this time is 2083 square meters, and the design concrete volume is 2600 cubic meters.

6 company, marking the completion of all raft pouring except for the reserved construction platform and the realization of important engineering nodes.

After 40 hours, the raft of this section was successfully poured, laying a solid foundation for subsequent construction.

At present, building 1 and building 2 are under construction on the second floor, building 3 is under construction on positive and negative zero, building 4 is under construction on the first floor, and building 5 is under construction on the second floor…

On June 17, the raft of Building 5 and surrounding garages was successfully poured for the West Railway Station resettlement area 2 and lot 3 project of China Railway Beijing Engineering Bureau No.

The project management personnel monitored and controlled the whole process of concrete pouring, vibration and surface finishing, ensuring the process connection and construction quality.

Lifting Anchor

The project department fully prepared and carefully organized the technical safety disclosure to the construction personnel, and strictly accepted the reinforcement and formwork.

During the construction, 2 pump trucks and 16 tank trucks were operated at the same time.