Information tips were added, and electronic labeling and manual inquiry services were provided on various channels, such as map navigation manufacturers such as Gaode, Tencent, Baidu, ticketing software, Leshan heart to heart service hotline, to guide citizens to travel off peak and detour in advance.
On June 24, at the news briefing on the work of easing congestion and ensuring smooth traffic in the main urban area during the construction of the second Minjiang River Bridge in Leshan, Leshan Municipal Bureau of housing and urban rural development, traffic police department and transportation department gave detailed answers to the problems that the public are very concerned about, such as the necessity of reconstruction, the detour scheme of some key sections, and the preparation before construction.
If temporary road occupation is required during the construction process, or power, water and gas supply are required in case of emergencies, the construction unit has also developed corresponding emergency plans, such as reserving access roads, making public announcements in advance, changing public transport travel routes, etc., so as to notify residents in advance to take measures to cope with life and travel, so as to reduce the impact on the life and travel safety of surrounding residents.
In the process of construction, the construction work will be carried out as far as possible to avoid the time when people live intensively, and the mechanical equipment with low noise and low vibration will be used as far as possible.
During the construction period, the traffic police department will strengthen the persuasion of traffic violations such as illegal parking within the construction area.
In case of serious congestion in the main urban area of Leshan, the traffic entering the city towards Shizhong District shall be intercepted in Jingyan County, Wutongqiao District, Shawan District, Jiajiang County, etc., so as to quickly evacuate the traffic flow in the city, avoid the aggravation of congestion and spare no effort to alleviate the congestion in the central urban area caused by construction.
At present, according to the overall idea of near end control and far end detour, the work plan and emergency plan for slow blocking and smooth traffic flow have been formulated.
At the same time, wet operation will be widely used in various processes to strictly control the generation of dust.
overpass), both of which are asphalt concrete pavement.
They can bypass the third and fourth Minjiang River bridges in Leshan or pass through the expressway..
Please mark the detour plan ↓↓ from June 27, the East Bank of Leshan Minjiang second bridge will be closed for construction! Please stagger the peak and take a detour! 04 how to guide citizens and tourists to travel correctly? The traffic police department said that it would strengthen publicity, improve public awareness, advocate green travel, encourage people to take buses or share bicycles in cities, and reduce driving.
02 how to effectively reduce the impact on the living environment and travel of the surrounding people during the project construction? According to the relevant person in charge of Leshan Municipal Bureau of housing and urban rural development, in view of the dust raised during the construction process, such methods as enclosure spraying, atomization and dust reduction, and cleaning of construction vehicles in and out will be adopted for dust reduction.
In addition, optimize the traffic signal timing of key roads (such as Hanlin Road, Fenghuang Road north section, Baiyan Road North Section in Tongjiang District, Hexiang road in Qingjiang District, roads around Xincun in the old urban area and their connecting Chunhua road and Jiading Road) within the radiation range of the construction core area of Leshan main urban area, so as to balance the traffic flow in the urban area and avoid large-scale and long-term congestion in the urban area during peak hours.
At the same time, strengthen the road traffic guidance of Leshan Giant Buddha Scenic spot.
03 how to effectively alleviate traffic congestion during construction? The relevant person in charge of the traffic police detachment of Leshan Public Security Bureau said that since the road closure construction will cause great changes to the traffic flow through the second Minjiang River Bridge in Leshan, it is expected that the traffic in the construction area will be more congested than usual.
01 how is the preliminary preparation of the project? The relevant person in charge of Leshan Municipal Bureau of housing and urban rural development said that the project was scheduled to start on-site encirclement and control at 10:00 after the morning peak on the 27th of this month.
The reconstruction starts from the traffic light at the bridgehead on the East Bank of Leshan Minjiang second bridge, crosses Bishan Road, connects Foguang Road, and ends at Qingguan Road (Leshan Friendship Hospital) under planning, with a total length of about 0.77 km.
After the completion of the project, it can greatly optimize the traffic network in the east of the city, alleviate traffic congestion, improve the travel convenience of the masses, improve the efficiency of entering and leaving the city, and further promote the economic and social development of Leshan City.
At present, the traffic police department is gradually improving the traffic control work before the traffic closure to ensure that all the surrounding control work will be improved before June 27.
In the core construction area, slow entry and fast exit have been carried out, and vehicles have been controlled and induced to bypass the belt Expressway and Leshan Minjiang fourth bridge at the remote end at the hierarchical level.
According to the traffic organization plan, 88 traffic signs and signs for guidance and indication shall be set up, 160m wave protective fence and 60 sets of warning lights shall be installed to guide vehicles to avoid the construction area and bypass the first, third and fourth bridges of Minjiang River in Leshan.
In the construction affected areas, increase the coverage of scientific and technological law enforcement equipment, send more patrol police, increase the persuasion of traffic violations such as illegal parking and retrograde traffic, and standardize traffic order and driving safety.
For the roads in the scenic area affected by the construction, a variety of ways are adopted in important holidays to guide and prompt the tourist vehicles in the Laile Giant Buddha Scenic Area to the scenic area through the Giant Buddha toll station on the expressway as far as possible, so as to avoid aggravating the road congestion in the scenic area.
The road plane is divided into elevated layer and ground layer (i.e.
05 how to bypass the transit vehicles that used to drive to Jingyan county and WUTONGQIAO district through the second Minjiang River Bridge in Leshan? The traffic police department said that the car owners should make a detour plan in advance.
At the same time, the housing and urban rural development department, together with the municipal traffic police, transportation, urban management and other departments, has jointly formulated and improved the traffic organization plan during the construction of Quanfu connecting line, and the site has gradually started to implement the traffic organization plan according to the plan.
Please click the blue character above to join Qianwei fellow villagers’ group! Phase II of Leshan urban connection line project of Expressway (Quanfu connection line) will be officially implemented on the 27th of this month.
Therefore, in terms of traffic control, according to the actual situation, the general principle of “first remote end, then near end, first prompt, then construction” will be adopted.
In the early stage of construction, the transplanting of street trees along the road, the removal of central guardrail and separator have been completed, creating conditions for the project owner to enter the site for construction.