It is understood that the relocation project of Dagang covers an area of 5590 mu, which is the largest earthwork project in Sichuan Province in recent ten years.
The site leveling project, a key basic project for the relocation of Dagang steel to other places, is planned to be completed and delivered on June 30 this year.
According to lvsonghe, director of the project engineering department of China 19th Metallurgical Group, who undertook the construction, the current construction method is “5+2, white plus black, 24-hour uninterrupted construction”.
The total excavation volume of the site is 17.8354 million cubic meters (including topsoil), the total filling volume is 15.2296 million cubic meters, and the removal volume of soft soil is 2.3263 million cubic meters.
[special statement] the content of this article comes from Dazhou observation, Dazhou palm, Dazhou release, southwest iron and steel index, etc.
The maximum excavation height of the slope is about 130 meters.
It is understood that since the commencement of the site leveling project of Dagang, the construction unit has been working hard day and night to ensure quality, safety and progress, and set off a new upsurge of site leveling construction.
The views and positions of this article do not represent those of this official account.
More than 1500 machines are put into the front line every day, with more than 1800 construction personnel, more than three times the previous work efficiency.
have entered the countdown sprint in an all-round way, and the daily excavation volume has reached the peak of 500000 m3.
The copyright of this article belongs to the original author.
According to the design of 13 steps, the maximum filling height of the site is 15 meters.
if there is any infringement, please contact to delete it.
Zhushouwen, a staff member of the park construction bureau of Dazhou Eastern Economic and Technological Development Zone, said that at present, the eight work areas of Dazhou iron and Steel Co., Ltd.
If other third parties want to.
The whole project is operating at full capacity, and we are confident to achieve the “6.30” goal.
At present, the project department focuses on the goal and starts the “white plus black”, “5+2” and “three shifts” uninterrupted operation mode, racing against the clock to catch up with the schedule and working overtime to make every effort to ensure that the goal is completed on schedule.
As of June 8, the total excavation volume of the site has reached 14.0958 million cubic meters, and the total filling volume has reached 11.49 million cubic meters.
At 6:30 a.m., Chen Ming, the excavator driver who has been busy all night on the site of Dagang steel, and the workers who took over the post completed the shift, Nearly 700 builders like him have shuttled back and forth in eight operation areas and completed nearly 170000 cubic meters of excavation and filling.