Bailai reservoir: seize the construction of diversion works and strive to close the river in October

On the other hand, at the site of plot B in shennei resettlement area, the reporter saw that excavators and transport vehicles were shuttling back and forth, workers were stepping up construction, and the scene was full of hot construction.

It is reported that by the end of May 2022, the total investment completed for the Bailai water control project was 8.98 billion yuan, accounting for 62.93% of the total investment in the approved estimate of the project.

In addition, the construction unit of Jiandou waterworks has entered the site for surface cleaning, and the groove inspection of retaining wall foundation has been completed; The relocation and reconstruction project of Jiandou New Town section of County Road 340 completed the setting out of the 5.237km red line of the whole line and the excavation of 19000 cubic meters of Subgrade Earthwork.

The sand and gravel production system and concrete mixing system located 1 km away from the left bank upstream of the dam have also been put into use.

It is reported that in March 2021, the dam foundation of Bailai water control project was officially excavated, and the left bank entered the construction period.

Once excavated to the right bank, it can be in a relatively waterless environment, which is convenient for the subsequent excavation and construction of the right bank of the dam.

Ma Dong also said that the construction of 12\n\e diversion bottom outlet dam block pouring and diversion open channel currently under way is a key construction stage.

Zhanghuaibin said that in the next stage, supporting public construction projects such as primary schools, kindergartens and farmers’ markets in the resettlement area will be gradually promoted to improve infrastructure and ensure a good production and living environment for immigrants.

Recently, at the construction site of the main dam project of the Bailai water control project, the reporter saw that the construction team was overcoming the influence of the weather, seizing the construction period and making every effort to promote the project construction.

In January this year, the first concrete warehouse of the main structure of the dam was poured.

Plot D is in the process of finishing decoration and outdoor works.

The construction of the other 9 plots has been started successively from February to June this year.

In addition to the main body of the dam under construction, the dam access road and “two stations and one park” projects in the C1 bid section of the project have been basically completed, with an investment of 67.31 million yuan.

“Now accelerate the construction of resettlement areas.” When arriving at the resettlement building in plot e03-01, some of the construction teams are laying floor tiles and wall tiles, and some are installing stainless rod railings for stairs and balconies.

Source: Anxi news..

Over time, the resettlement area has been promoted to build new primary schools, colorful kindergartens, bright health centers…

Speed up the construction of reservoir diversion works.

A modern Jiandou new town with tea characteristics is accelerating its formation.

“There are 10 resettlement plots in the resettlement area.

The highlights are about to be presented, such as formwork erection, reinforcement binding and concrete transportation…

“According to the current weather conditions, we will simultaneously promote the construction of indoor decoration and outdoor projects to ensure the completion on schedule and ensure the smooth progress of the Bailai water conservancy project.” The relevant person in charge of e03-01 plot said that the plot has a total construction area of 95582 square meters, and it is expected that the preliminary acceptance of the projects under construction will be completed by the end of July.

Construction forces will be actively invested.

Elephant Foot Ferrule

The project party plans to excavate the right bank of the dam in early October to jointly open the construction faces of the left and right banks.

“The business buildings of Jiandou Town Central Primary School, central kindergarten, Jiandou health center and police station have passed the pre acceptance, and the construction of county No.

Measures such as optimizing construction organization design, increasing resource investment and 24-hour uninterrupted operation will be taken to speed up the construction period and speed up the progress, so as to strive for the smooth closure of the river in October this year.

“At present, the focus is on the water intake of diversion open channel, with a floor of 3M, which needs to be constructed to the technical level of the drawing to prepare for subsequent works.” At the site of section C2 of Quanzhou Bailai water control project, Ma Dong, deputy general manager of the project investment and Development Co., Ltd., told reporters.

After the completion of shennei resettlement area, it can accommodate 17500 people in the reservoir area.

At present, the earthwork and foundation works are being promoted simultaneously.” Zhanghuaibin, engineer of dabailase shennei resettlement office, introduced that all the projects are advanced over time on the basis of ensuring construction safety and project quality.

In 2022, it is planned to invest 2.5 billion yuan, and 1.045 billion yuan has been invested, accounting for 41.8% of the annual plan.

“The river closure is planned for October, so the construction of diversion works must be completed before the river closure.” Ma Dong said that the purpose of river closure is mainly to carry out flow through the diversion bottom outlet.

Now they are mainly engaged in the construction of environmental protection measures such as dust removal; the ‘two stations and one park’ has been basically completed, and the rest of the greening works are being completed; the dam management room has been settled and put into use; and the fish breeding station has been completed.” Introduction to Ma Dong.

12 middle school has been basically completed.” Chen Hesen, the person in charge of the site, said that as of May, about 169.33 million yuan of construction investment had been completed this year, including 4 basically completed projects, 18 projects under construction and 14 early-stage projects.

“These two systems have been put into use, and their production capacity meets the requirements of the current construction site.