According to the unified arrangement of the municipal government, the construction of Zhongshan Road renewal project is planned to start at 22 p.m.
Please support and understand the inconvenience caused by road construction.
Among them, the first four phases will occupy a row of motorways and part of the slow lane on the curb side by side for the reconstruction of the motorway, the reconstruction of the slow lane and the construction of pipeline replacement, with a construction period of 100; In the fifth phase, the whole line will be milled and covered at night, with a construction period of 15 days.
Liaoshen Third Street will be constructed in half sections.
Steel plates will be laid and speed bumps will be installed during the day to ensure normal traffic during the day.
The construction time is 22:00-5:00 the next day.
It will occupy the motorway with a width of 0.7 meters under the curb on both sides of the road and the brick road above the curb for green belt replanting, curb replacement, sidewalk reconstruction and well circle adjustment.
The Zhongshan road renovation project starts from Shengli Street in the west to Nanjing Street in the East, with a total length of 1066 meters, and will be constructed in five phases.
From July 8 to July 17, 2022, the construction of gas pipeline replacement will occupy the west entrance of Liaoshen Third Street on Northeast Avenue and cross Liaoshen third street.
▌ source of material: Shenyang release, Shenyang traffic police, photo network, image worm creativity, etc.
Tuchong creative -472237744520429571- irrelevant to the picture and text.
During the construction period, vehicles can bypass Shenying street and Caixia street.
if there is infringement, please contact to delete.
The above schedule may be advanced or delayed according to the overall progress of the project.
The construction period is 54 days.
During the construction period, the original West to East vehicles need to bypass Jinshan Road.
According to the unified arrangement of the municipal government, the construction of Taishan Road and Street Renewal Project in Huanggu District is planned to start at 22 p.m.
on July 8, 2022 to 24 p.m.
on July 23, 2022, and adjust it to East-West one-way traffic.
Figure insect creative -772837566353244178- the construction of gas pipeline replacement on Northeast Avenue is irrelevant.
on July 8, 2022, and organize the implementation of Zhongshan Road renewal project in Heping District, which is expected to end on October 31, 2022.
on July 8, 2022, and organize the implementation of Taishan Road and Street Renewal Project in Huanggu District, which is expected to end on August 30, 2022.
Taishan Road Street renewal project starts from Beiling Street in the west to Lingdong street in the East, with a total length of 1200 meters.
Guys, look here! Recently in Shenyang, please pay attention to safety when these roads need to be constructed! Road reconstruction project of Lane 2, LiNbO Road, Hunnan District in order to ensure the smooth progress of the road reconstruction project of Lane 2, LiNbO Road, Hunnan District, according to the unified arrangement of the municipal government, the two-way motor vehicle traffic from Mingbo road to LiNbO road of Lane 2, LiNbO Road, will be closed in sections from July 8, 2022 to August 11, 2022.
Please pay attention to the adjusted traffic instructions.
In order to ensure the smooth progress of the construction project of Jinshan North Road Station of Metro Line 6, according to the unified arrangement of the municipal government, it is now decided to close the West-East motor vehicle traffic at the east entrance of Yalujiang North Street on Jinshan North Road from 21 p.m.
During the construction period, vehicles on Liaoshen Third Street will be guaranteed to pass.