It is expected to end on September 14, 2022, with a construction period of 60 days.
Pedestrians and non motorized vehicles pass above the kerb.
It will occupy two rows of motor vehicle lanes on the south side of the road for the construction of new external power supply.
One row of lanes will be set in the north-south direction, and two rows of lanes will be set in the South-North direction.
The road renovation project of Xijiang Street starts from the second ring road in the north and ends at Xinkaihe bridge in the south, with a total length of 2.4 kilometers.
Phase I: from July 15 to August 14, the eastern half of the motorway from the second ring road to Xinkaihe bridge will be occupied, and the remaining three lanes in the western half will be used for two-way traffic of motor vehicles.
From July 15 to August 14, 2022, the milling cover and pest treatment project of Yulin Street will occupy a row of motor vehicle lanes at night (from 22:00 to 5:00 a.m.
Phase II: from August 15 to September 14, the eastern half of the motorway will be occupied, and the remaining three lanes in the western half will be used for two-way traffic of motor vehicles.
Phase IV: from October 1 to October 15, the West sidewalk will be occupied, and the sidewalk will be adjusted to be mixed with non motor vehicles under the curb.
Pedestrians and non motor vehicles will pass above the curb.
The Changjiang street road renovation project is divided into two sections.
The second section starts from the second ring road in the north and ends at Xinkaihe bridge in the south, with a total length of 21 kilometers.
to 16:00 a.m.) for covering operations, and motor vehicles will be organized to pass in two-way two lanes in opposite directions.
The construction of the track project of shifuda Road Station of Metro Line 4 will occupy the North ninth road to the North eighth road of Nanjing North Street.
on July 15, 2022, which is expected to end on October 15, 2022, with a construction period of 3 months.
Phase III: from September 15 to September 30, the West sidewalk of Lushan road to Huishan road section and the second ring road to Xinkaihe bridge section will be occupied, and the sidewalk will be adjusted to mix with non motor vehicles under the curb.
Phase I: from July 15 to August 14, the west half of the motor vehicle lane will be occupied, and the remaining east half of the three lanes will be used for two-way traffic of motor vehicles.
Phase III: from September 15 to September 30, the sidewalk on the east side will be occupied, and the sidewalk will be adjusted to mix with non motor vehicles under the curb.
The construction period of the external power supply project of Santaizi main substation of Metro Line 2 is 60 days.
According to the unified arrangement of the municipal government, the municipal urban construction department plans to organize and implement the renovation project of Changjiang street road from 9 p.m.
Recently, many roads in Shenyang are under construction, so we must pay attention! According to the unified arrangement of the municipal government, the municipal urban construction department plans to organize and implement the road renovation project of Xijiang street from 9 p.m.
2.
The construction of shifuda Road Station of Metro Line 4 will occupy the road from July 15 to December 30, 2022.
After the completion of construction, half of the road will be closed during the day (from 9:30 a.m.
The existing enclosure on the east side faces the west 3 rows of motor vehicle lanes, and the existing enclosure on the west side backs the 3 rows of motor vehicle lanes to ensure the passage of two-way 8 rows of motor vehicle lanes.
Source: Liaoshen Evening News, Shenyang bus network..
The motorway and sidewalk will be renovated and constructed, and the project will be implemented in four phases.
It is only for the renovation of sidewalks.
The road renovation construction is carried out in four phases.
The motorway under the stone on the west side in front of Nanjing South Street foreign language school.
The construction period of Yulin street is 30 days.
During the construction period, the machine and non machine isolation guardrail is specially added to ensure the traffic safety.
on July 15, 2022.
During the construction period, machine and non motor isolation guardrails will be added to ensure traffic safety.
on July 15, 2022, which is expected to end on October 15, 2022, with a construction period of 3 months.
The first section starts from Lushan road in the north and ends at Huishan road in the south, with a total length of 550 meters.
According to the unified arrangement of the municipal government, the municipal urban construction department plans to organize the implementation of the external power supply project of Santaizi main substation of Metro Line 2 from 10 p.m.
The construction period is 30 days, and the construction period will be postponed in case of rain.
Phase II: from August 15 to September 14, occupy the west half of the motorway from the second ring road to Xinkaihe bridge, and the remaining east half of the three lanes for two-way traffic.
From July 15 to August 30, 2022, the relocation project of power and water supply pipelines of Shayang Road Station of Metro Line 4 is under construction.
The construction of Shayang Road Station of Metro Line 4 is occupied.
the next day) for milling operations.
The external power supply project of Santaizi main substation of Metro Line 2 is located in Songshan West Road, starting from Ningjiang street in the west to Nujiang street in the East, with a total length of 1200 meters.
Phase IV: from October 1 to October 15, occupy the eastern sidewalk of Lushan road to Huishan road section and the second ring road to Xinkaihe bridge section, and adjust the sidewalk to the bottom of the curb, mixed with non motor vehicles.
One row of lanes are set in the north-south direction, and two rows of lanes are set in the south-north direction.
The renovation period of Changjiang street road is 3 months.
Construction occupation: 1 The motorway under the stone on the west side of Nanjing South Street (the general staff office building at the east gate of Shashan Park).