The construction unit responded: is it unprofessional or “barbaric” construction to cut off the water pipe six times in Hancheng road?

During the excavation process, we will send special personnel to command the work, and coordinate with the pipeline property right unit to arrange special personnel to guide the construction and emergency repair on site, and try our best to do a good job in the protection and monitoring of the original pipelines, Try to avoid the inconvenience caused to surrounding residents by pipeline damage and too long repair time.

Next, in the excavation and construction of the remaining few pipe network trenches, our company will continue to operate according to the regulations and carry out careful construction with the strong support of the pipeline property right unit.

Anhui Hutong Construction Engineering Co., Ltd.

Dear Susong people forum netizen: Hello! First of all, I deeply apologize for the inconvenience caused to you and the surrounding residents by our company’s cutting of the water pipe during the construction of Hancheng road.

Third, the underground pipelines within the construction scope of the project are complex, there are no obvious signs on the ground, and there is no relevant positioning map to guide the construction underground for a long time.

Before excavation, we will do a good job in technical disclosure and emergency repair plan.

July 27, 2022..

Secondly, although our company is cautious and cautious about water, electricity and other livelihood pipelines and hazards, there are still some imperfections to be improved in the construction process.

Erection Anchor

Although we operate carefully, we still cut the underground pipelines from time to time, which is really not intentional.