This year’s summer maintenance work is nearing the end, and the heating season is nearing.
We continue to work hard and sweat to ensure the efficient implementation of the “winter sickness and summer cure” maintenance work.
1、 Safety: in August, the production department continued to implement the safety tasks assigned by the group company, insisted on holding departmental safety meetings every week, carried out irregular safety inspections on various projects, made inspection and registration on the construction site, and pointed out the problems found in time for rectification.
In the middle of August, the beginning of autumn has passed, and the weather is gradually getting cooler.
Next, our company will organize the construction party to hold project quality and safety meetings, strengthen on-site inspection and personnel safety education, and resolutely ensure safety, quality and construction period.
are signing outsourcing construction contracts, The maintenance work was carried out according to the specified schedule, which laid a good foundation for the heating work this winter.
Taking advantage of the golden time of summer maintenance, all operation and maintenance personnel work hard in order to speed up the progress of maintenance.
Colleagues, 12 technical transformation projects will be implemented this year, including the transformation of Shuimu Qinghua, Renjiazhuang, Kangxin Huayuan, post office heat exchange station, the transformation of circulating pump and the automatic control transformation of chemical water workshop.
2、 Engineering: the production department has conducted on-site exploration for this year’s expansion project for many times to confirm the location and route of the heat exchange station, repeatedly visited the site and went to the site, actively contacted the site personnel, fully understood the design intent, comprehensively summarized the problems and determined the implementation plan.
Working overtime is just a microcosm and a normal thing, but they never complain.
The remaining automatic control, instrument water and electricity, soft water transformation, valve transformation, etc.
A drawing is always changed and changed.
By the end of July, 453 maintenance items have been completed, and the plate replacement and cleaning, valve maintenance and pump maintenance of each heat exchange station have been basically completed.
In the high temperature of more than 30 degrees Celsius, we are not afraid of being dirty and tired.
As of July, 13 expansion projects have been approved and the design entrustment of the confirmed projects has been completed.
Various new expansion, technical transformation and maintenance projects are in full swing, and the work of the production department is gradually pushed forward in an orderly manner.
3、 “Winter disease and summer treatment” work Hejin company plans to overhaul 721 items this year, which are divided into three categories: routine maintenance, plate replacement cleaning and outsourced maintenance.
In the next step, while promoting the completion of the independent maintenance work, we will focus on strengthening the safety and construction quality inspection of the outsourced construction site, making a daily inspection diary, and requiring the construction party to rectify problems in time to ensure that all projects are completed on schedule…