Personal housing construction contract word file download

The side walls and back walls are all brick to the top of the cement.

The board and lodging expenses of the construction personnel shall be borne by Party B, and the expenses of machinery and equipment, formwork and scaffolding used in the construction shall be borne by Party B.

The contract shall take effect from the date of signature.

Two layers are added on the basis of the existing one layer.

♩ ~ ♩.

3.

The indoor mortar is flat without bursting.

contracting method: Party A’s building additional layer construction project is contracted to Party B in the form of contracting labor but not materials.

Click the blue word to pay attention to us in case of unexpected needs Party A (employer): XXX Party B (Contractor): XXX Party A will contract the original building storey construction project to Party B.

The roof is flat without water leakage.

♩.

4、 Before the commencement of the project, Party A shall be responsible for connecting water and electricity, and preparing construction materials such as reinforcement, cement, sand, stone and wood in advance according to the progress of the project.

Through negotiation, both parties have reached the following agreements: I.

♪ ~ ♬..

Ringlock Scaffolding System Ledger End

2.

♩.♬♬♩♩♩♩♩♪♬♩♩♬♩♩♩♪♬♩♩♩♩♩♩♩♩♩♩♬♩♩♬♩♩♩♬♩♩♩♬♩♩♩♬♩♩♩♬♩♩♩♪ ♩~ ♬♩♩♩♩♩♪♬♩♩♩♩♩♩♩♩♩♩♩♩♩♩♩♩♩♩♩♩♩♩98..

The total construction cost is 23000 yuan.

The project contracting method is labor contract without material contract, which is calculated according to the actual construction area.

2、 Project content: 1.

It is priced at 140 yuan / m2 according to the actual construction area.

All of them are tiled.

♩.

10000 yuan is paid in advance for commencement, 10000 yuan is paid in advance after tile laying, and the rest is paid in a lump sum after acceptance.

5、 Calculation of project cost: 1.

♩ ~ ♪ ~ ♬..

2.

♪ ~ ♬.

The standing timber is delayed due to the high-voltage line, and 1000 yuan is added.

The exit and return water eaves are 1.2 meters high and 50 cm high.

7、 This contract is made in duplicate, with each party holding one copy.

♩ ~ ♪ ~ ♩.

The main part is required to be a sloping tile roof.

There are two doors and three windows in front of the house.

♩ ~ ♩.

matters not covered herein shall be settled by both parties through negotiation.

Party A: Party B: Negotiator: mm / DD / yyyy ♪ ~ ♬..

♩ ~ ♪.

♩.

Party A shall bear the water, electricity, building materials and freight during the construction.

From the commencement of the project to the completion of the project, Party B shall be fully responsible for the personal and property damage of the construction personnel and the third party other than the construction personnel caused by Party B during the construction process, and Party A shall not bear any responsibility.

3、 Construction safety: Party B is responsible for safety production during construction.

Vi.

♪ ~ ♬..

♩ ~ ♬.