Party B shall provide living expenses by itself, and Party A shall not advance living expenses.
Party B must carry out regular safety education for the construction personnel of the shift, adhere to the task handover before and after the shift, and regularly check the shelves and boards of the construction parts of the shift before and during the construction, so as to achieve safe construction.
♪ ~.
♩ ~.
Iron wire, nails and other consumables required for formwork installation.
♩ ~.
♪ ~.
Machinery and installation (excluding electricity) required for formwork works.
♩ ~.
♬..
6、 Responsibilities of Party B: 1.
5、 Party A’s responsibilities: 1.
♬.
♬..
♬ ~.
If it cannot be completed as planned, a fine of 300 yuan / day will be imposed, and so on.
♬.
8、 Construction period management and others: 1.
all formwork works of foundation and main body.
♩ ~.
If Party B fails to work overtime to catch up with the progress according to the working hours, Party A is responsible for arranging electricians to install lighting and personnel to cooperate with the construction, but Party A cannot ask for night shift subsidies for such overtime.
Party A: Party B: month, year.
Carry out technical disclosure to Party B according to the construction specifications and technical requirements, and provide a set of construction drawings; 2.
contracting content a.
♪ ~.
♩ ~.
♬..
2.
1、 Project Name: II.
♩ ~.
♩ ~.
If Party B completes the construction task through overtime, it can be seen that it is completed on schedule; 3.
♪ ~.
Abide by national policies, regulations and the company’s management system, and obey the unified dispatching of the person in charge on site; 2.
♪ ~ ♬..
Including setting out, internal scaffold support, formwork cutting, fabrication, installation, horizontal and vertical transportation in the site.
The person in charge of the site finds that Party B violates the rules and regulations and is fined 200 yuan at a time.
Carefully read the drawings, carefully construct, and successfully complete the construction task of this type of work according to the requirements of construction drawings and technical disclosure; 3.
♩ ~.
In case of rework during construction, in addition to the rework cost, the material payment shall be compensated.
♪ ~.
Party B must carefully construct and carefully cut materials according to the dimensions shown in the figure and the requirements of technical disclosure, and do not waste materials.
♩ ~.
♬.
♬.♪ ~ ♬….
Party B is responsible for the education and inspection of the safety management work of the team, and the operation and construction are carried out in strict accordance with the national safety rules and regulations.
♩ ~.
C.
If Party B has a major safety accident due to violation of regulations during construction, Party B will be responsible for all the responsibilities of this accident.
10、 Project settlement and others: 1.
Party B cannot leave the site midway for any reason.
4.
Party B must organize labor mobilization according to the construction period deployed by Party A, and actively complete the construction tasks of the type of work on schedule before the specified time.
♩ ~.
♩ ~.
Click the blue word to pay attention to us in case of need Party A: (hereinafter referred to as Party A) Party B: (hereinafter referred to as Party B) Party A is now undertaking the project, with a construction area of about 1500 square meters.
♩ ~.
The formwork installation should be firm, standardized and shaped, and should ensure that it meets the requirements of acceptance specifications.
Party A pays 10% of the total amount of the project after the completion of Party B’s foundation formwork, 20% of the total amount after the completion of the first floor, 20% of the total amount after the completion of the main body, 40% of the total amount after the structural acceptance, and the remaining 10% is paid in a lump sum after the completion and acceptance of the main body.
2.
♩ ~.
in order to clarify the responsibilities of both parties, ensure the project quality, speed up the project progress, and successfully complete the project task, the following terms are hereby agreed by both parties.
♪ ~.
Be responsible for the pre job education, pre shift disclosure, and safety self inspection before and during operation of the construction personnel of the team; 6.
♩ ~.
♬.
4、 Contract price: 63 yuan per square meter of building area, and the building area is subject to the total building area of the design drawing; In case of major changes in the project, the change cost will be negotiated separately.
♬.
♬.
It will come into force after being signed by both parties, and will become invalid after the settlement and payment of the project completion.
Contracting method: contract labor but not materials III.
If Party A fails to provide materials in time, causing Party B to stop work for one day, the construction period shall be postponed, and the living allowance of 20 yuan / person per day shall be given to Party B’s actual construction personnel on site.
After each layer is completed, it shall be cleaned in time, otherwise a fine of 100-500 yuan will be imposed depending on the circumstances; 2.
7、 Project quality and others: 1.
Actively organize enough skilled workers to enter the site according to the notice of Party A, and ensure that the construction tasks are completed according to the construction period required by Party A; 4.
♬ ~.
B.
9、 Safety management and others: 1.
♬.
♬..
If Party B leaves the site midway, Party A has the right to investigate and claim compensation for the losses caused by Party B’s Midway exit, in addition to not paying wages.
♩ ~.
11、 Others: this agreement is made in duplicate, with Party A and Party B holding one copy respectively.
After negotiation, the sub project of the project template is assigned to Party B.
♩ ~.
♩ ~.
♬ ~ ♩ the ball shares the ball and likes the ball..
♬.
♬.
2.
♩ ~.
♪ ~.
Be responsible for the timely supply of various materials required for the construction of the project; 3.
♬.
♬..
Provide daily necessities for food and housing and necessary construction tools; 5.
♬.
3.
♩ ~.
♬…
♬..
If the construction cannot be carried out normally due to weather, the construction period shall be postponed.
Party B shall be settled in time according to the provisions of the contract.
Party B must carry out civilized construction and ensure that the site is clean after the completion of the work.