If there is any infringement, please contact the deleted manuscript to get the emergency and news in Shenyang at the first time.
The East-West motor vehicle traffic will be closed; Phase II will occupy a 100m long road on the east side of Fangqing South Road and Fangqing North Road Beikou road.
The copyright belongs to the original author.
The first phase starts from Fangqing North Road in the West and ends at the west side of lane 25 of fangjialan road in the East, with a total length of 480 meters.
The sewage pipeline reconstruction project of Fangqing South Road will be carried out in two phases.
It is expected to end on October 25, 2022, with a total duration of 40 days.
According to the unified arrangement of Shenyang Municipal Government, the municipal urban construction department plans to start at 22:00 on September 16, 2022, and organize the implementation of the sewage pipeline reconstruction project of Fangqing South Road.
Source: Traffic Police Bureau of Shenyang Public Security Bureau.