It is estimated that the construction of the main pavement will be completed by the end of November, which is ready for traffic.
Construction site.
Click below 👇 Follow me and add stars ★ Source: Maoming Daily Disclaimer: Our institute.
It is designed as an urban trunk road, with eight two-way lanes, a red line width of 45 m, a design speed of 40 km/h, and asphalt concrete pavement structure.
After the completion of the project, it will be connected with Dongyue Road and Maoming Avenue to ease the traffic jam on the 10th Road of Youcheng, further improve the road network structure of Maodong District, expand urban arteries and development space, and promote urban expansion and quality improvement.
While focusing on safe production and project quality, it will urge the construction unit to seize the favorable weather, increase the investment of funds and machinery personnel, scientifically coordinate and reasonably arrange to accelerate the construction progress, ensure that the project completes the construction task on time, strive for the early completion and opening of the whole line to traffic, and make the public travel more convenient and fast.
Construction site.
Guanshan Seventh Road (Maoming Avenue Dongyue Road) is located in the east of Maoming downtown, running east-west.
In the next step, the project construction unit, the Municipal Development Group, will, according to the work deployment of the municipal party committee and the municipal government, work on the wall chart.
How is the current progress? On the afternoon of the 17th, the reporter learned from the interview at the construction site that the construction of the main road surface of Guanshan 7th Road is expected to be completed by the end of November this year, which is ready for traffic.
According to the construction party, since the mobilization, with the strong support and coordination of the municipal party committee, the municipal government and relevant units, the main road surface of Guanshan Seventh Road has been fully connected, special subgrade treatment, cement stabilized layer, pavement of the north side sidewalk of the road project have been completed, and the water supply and drainage works, planting of seedlings for greening works, and installation of street lamps for lighting works of Maoming Avenue East Guangdong section (580 meters) have been completed.
Yesterday afternoon, the reporter saw at the construction site of Guanshan 7th Road (Maoming Avenue – Dongyue Road) that the machinery was roaring at the site, the workers were paving asphalt in the east section of the road, and the road rollers were shuttling back and forth.
Guanshan 7th Road (Maoming Avenue Dongyue Road) in the urban area, as one of the important traffic networks in Maodong District, has attracted much attention since the construction began.
The project construction site is in full swing.
“We look forward to the early completion of the 7th Guanshan Road, which will greatly ease the traffic congestion in Donghui City and facilitate the travel of surrounding residents.” Liao, who lives nearby, said.
Project construction site.
The construction was intense, presenting a scene of vigorous activity.
It starts from Maoming Avenue in the west and ends at Dongyue Road in the east, with a total length of 792 meters.
The project has been steadily promoted as a whole, Up to now, the total construction progress is about 77%.
The project construction includes demolition works, road works, traffic works, water supply works, drainage works, lighting works, greening works, etc.
At present, asphalt paving of middle and surface course of road works is under way.