The university will move towards a high-quality development path, actively prepare for upgrading to the undergraduate level, add local advantageous majors, take engineering as the main subject, coordinate the development of multiple disciplines, and strive to build a model vocational college with distinctive features and high levels.
Phase I covers an area of nearly 730 mu, with an investment of more than 1.8 billion yuan.
It is estimated that the project will be completed in two to three years, and can accommodate 18000 to 22000 teachers and students by then.
The project plans to use about 1300 mu of land for construction.
The construction started this time includes 27 buildings, including teaching building, student dormitory, teacher dormitory, training building, fireworks art research building and teaching building, canteen, administrative complex building, student activity and foreign exchange center, with a total construction area of about 160000 square meters.
Wu Fang, president of Hunan Metropolitan Vocational College, said that the Liuyanghe Campus Project has entered the construction stage in an all-round way, which is a landmark project in the history of the school’s development.
(Rendering) In addition, the school has signed a school enterprise cooperation agreement with Liuyang Fireworks Association, which will promote the development of Liuyang fireworks industry.
It indicates that the construction of the new campus has entered the fast lane and will play a strong role in the overall development of the school.
Phase II covers an area of 310 mu.
(Renderings) After that, Puji Town will continue to make efforts to help Hunan Metropolitan Vocational College (Liuyanghe Campus) to complete the construction of Phase I of 160000 square meters in the first half of next year, so as to ensure that the college will start in the second half of next year as scheduled; Promote Hunan Metropolitan Vocational College to complete relevant land use procedures for Phase II and start the construction of Phase II project.
On the south bank of the Liuyanghe Puji section, with six construction teams and more than 400 workers stationed, the city’s key project, Hunan Metropolitan Vocational College (Liuyanghe Campus), has entered the construction phase in an all-round way.
The project of Hunan Metropolitan Vocational College (Liuyanghe Campus), which has received much attention from the public, has entered the construction phase in an all-round way.
Source: New Hunan, Liuyang Daily (reporter Mo Yu)..