Guide to construction data of hydraulic engineering

See the common form CB13 – Inspection Application Form for Construction Measurement Results of the Construction Contractor.

shall be submitted for inspection, and the mix proportion of mortar and concrete shall be made.

Commencement Application Form (contract project commencement form, unit project commencement application form, divisional project commencement application form), and attach the commencement application report.

Before commencement, cement, sand, crushed stone, admixture, etc.

After the workers enter the site, they shall timely collect their ID cards and post cards for registration, and do a good job in three-level education, safety technical disclosure, construction quality technical disclosure, and operation specification disclosure.

4.

See the construction company’s common form CB06 – Site Organization and Key Personnel Approval Form 3.

After entering the site, according to the control points handed over by the Owner, the site control network shall be established while reviewing the handover control points to form an inspection application form for construction measurement results.

See the construction company’s common form CB09 – Application Form for Advance Payment for the Project CB-10 Application Form for Advance Payment for Engineering Materials 15.

The label shall indicate the factory logo, steel number, product batch number, heat number, specification, size, etc.

Common Form CB01-I Application Form for Construction Technical Scheme of the Contractor for Approval of Safety Assurance System 9.

Common Form CB01-I Application Form for Construction Technical Scheme of the Contractor for Approval of Special Scheme for Temporary Electricity Use 7.

See the Contractor’s common form CB12 – Joint Survey Notice CB13 – Application for Inspection of Construction Survey Results.

17.

Make the raw material inspection account, including inspection date, batch, position, report results, etc.

Report for approval of special construction scheme and construction schedule (such as high formwork, deep foundation pit, tower crane, high slope, box culvert, flood discharge culvert, water receiving weir, footbridge, tractor bridge, grouting, cofferdam, steel sheet pile, etc.), see the common form CB01 – Application Form for Construction Technical Scheme of the construction unit.

See the Contractor’s Common Form CB14 – Application Form for Commencement of Contract Projects CB15 – Application Form for Commencement of Divisional Works.

Project advance payment application.

18.

Mix proportion, on-site rolling test and grouting test shall be submitted to the supervisor for filing after obtaining parameters.

The product quality certificate, factory certificate or test certificate and label of the reinforcement shall be collected when the reinforcement is submitted for inspection.

Common Form CB01-I Application Form for Construction Technical Scheme of the Contractor for Approval of Civilized Construction and Environmental Protection System 9.

Raw materials need to be submitted for inspection in a timely manner.

It is mainly the undisturbed topographic survey, which provides the basis for foundation excavation and calculation of earthwork excavation and filling quantities.

Form safety data record.

The construction organization design of general unit works shall be reported to the Chief Engineer Office of the Bureau for review and official seal.

The frequency of submission for inspection depends on the requirements of quality inspection.

Project division.

If necessary, experts should be invited to demonstrate.

Equipment entering the site shall be submitted for inspection (machinery, equipment certificate and inspection report shall be collected).

See the appendix for details.

6.

2.

Application Form for Construction Technical Scheme of the Contractor for Civilized Construction and Environmental Protection System.

Construction stage 18.

Click the blue words to focus on our construction preparation and pre commencement stage 1.

For example, the factory certificate, quality inspection report and cement inspection report of the quality inspection station shall be provided for cement; The ex factory certificate of cement shall indicate the variety, mark, factory name, ex factory date, magnesium oxide, sulfur dioxide content, loss on ignition, fineness, setting time, stability, strength and other indicators.

For construction machinery and equipment entering the site, such as hookers, bulldozers, trucks, pile drivers, road rollers, total stations, level gauges, etc., the total stations and level gauges shall be attached with periodic verification reports.

See the construction unit’s common form CB08 – Construction Equipment Entry Inspection Application Form.

shall be collected.

After the Supervisor has approved the construction organization design and issued the project commencement notice, the advance payment for the project or the advance payment for engineering materials shall be declared in a timely manner.

Lifting Socket

For projects with earthwork filling, the soil samples from the borrow area shall be submitted for inspection for indoor compaction test.

For sand and gravel, only the inspection report of the inspection station is required.

See the Contractor’s Common Form CB07 – Materials/Components and Fittings Entry Inspection Application Form..

The construction organization design, construction schedule of unit works, construction method of divisional works and construction schedule of divisional works are attached.

Before grouting, grouting test shall be carried out to obtain test parameters to guide construction.

After the compactness is tested, the on-site compaction test report shall be formed.

Common Form CB01-I Application Form for Construction Technical Scheme of the Contractor for Approval of Technical Quality Assurance System 8.

Generally, for projects involving major potential safety hazards, a special construction plan needs to be prepared, submitted to the Chief Engineer’s Office for review, and stamped with the official seal.

After the original data is measured, the calculation results shall be formed and submitted to the supervisor.

The construction organization design scheme is submitted for approval, and the construction schedule of unit works is submitted for approval.

For the submission of the construction scheme of divisional works and the construction schedule of divisional works, see the common form CB01 – Application Form of Construction Technical Scheme CBO2 – Application Form of Construction Schedule.

Joint measurement.

The Owner, the Supervisor, the Contractor and the design representative are required to participate.

The owner unit group shall organize the supervisor, the construction unit and the quality supervision unit to hold a meeting to determine the principle of project division, divide projects for quality assessment, designate unit projects, divisional projects and unit projects, and report to the quality supervision station for filing.

Layout of the survey control network.

After the soil samples are qualified, the site shall be arranged, the machinery and soil materials shall be organized for on-site compaction test, and the inspection station personnel shall be notified to take samples.

Collect the construction contracts (including supplementary contracts and agreements) to facilitate contract management.

16.

10.

The project organization shall submit for approval (that is, the members of the Project Department, including project managers, technicians, quality inspectors, safety officers, surveyors, constructors, documenters, etc.), and collect the professional title certificates, graduation certificates, identity cards, job certificates, and qualification certificates of the members of the Project Department, which shall be attached to the documents for establishing the Project Department.

Subdivide the unit project according to the division principle and code it.

See the attachment for coding description.

11.

13.

5.

Materials, components and parts shall be submitted to the site for inspection (such as reinforcement, cement, sand, gravel, geotextile, geomembrane, foam board, etc.), and factory certificates, quality inspection reports, etc.

12.